9/
20
16 © M
o
lo
k O
y
1.
Dig the installation pit according to the measurements
in the image 2. The pit should be 600 mm wider than the
diameter of the container. Level the bottom carefully with
spirit level and compact the ground if needed. (Image 3.1.)
Diameter of the installation pit:
MolokClassic®-container 5 m³
2150 mm
MolokClassic®-container 3m³ and 1,3 m³
1750 mm
2.
Preparing 800 l and 300 l containers:
Fasten the anchor steel into the bottom insert according to
a separate instruction manual provided.
Preparing 5 m³; 3 m³ and 1,3 m³ containers:
Fix the plastic bottom anchors into the container with two
bolts each (bolts are tightened max. 25 Nm). (Image 3.2.)
3.
Lift the container to the installation pit by using lifting
loops. The use of lifting beam is recommended (Image 3.3).
4.
Align the lid opening by using the sign in the
front panel.
5.
Use a spirit level to ensure the container is straight and level.
Depending on the installation site
, use the spirit level either;
A.
on top of the aluminium ring (lid and lifting
bag removed)
OR
B
. from the sides of the container
6
. Fill the pit as described in the image 2.
With a light compactor, compact the filling soil
carefully with every 200 mm layer. We recommend
to use max. 100 kg round compactor. (Image 3.5)
7.
Make sure that the finishing layer slopes slightly
downward from the container.
Image 3.1.
50 mm of 0-16 mm crushed
gravel can be used for levelling.
Image 3.2.
Fix the plastic bottom anchors
into the container using two
bolts.
Image 3.3.
Lift the container to the instal-
lation pit by using lifting loops.
Make sure that the container is
straight and level.
Image 3.4.
Fill the installation pit using
gravel 16-32 mm, ballast
material and suitable finishing
material.
Image 3.5.
Ballast material is then placed
on top of the crushed stone
(anchoring).
Use a spirit level to ensure the
container is straight and level.
Image 3.6.
Remove the plastic covers.
Picture 3.7
Remove the lifting loops.
Picture 3.8
Open and straighten the
lifting bag before placing it in
the container.
page
2
/
2
Additional pictures for instructions given on pages 2 and 4.