4. Install two previously removed M10 shipping screws back into the vertical
beam and tighten.
5. Carefully insert, and thread, all nine M12x35 socket head caps screws
(SHCS) bolting the upper and lower beam together.
a) Loosely tighten the SHCS in the order shown. This order is important
to draw the vertical beam squarely into position.
#1 (both sides)
#2 (both sides)
#3 (both sides)
#4 (both sides)
#5
(beneath
center)
b) Torque to half the recommended torque setting, following the same
order as shown. See “Screw Torque Specifications” on page 9-1.
2
3
1
1. Lifting with tension in rear sling
2. Approximate tipping point
3. Lowering with tension in forward
sling
E-Multi Radial Installation (EM1 and EM2 Models) -
continued
Figure 11-6 Tilting the E-Multi Radial from the horizontal to vertical position
11-7
E-MULTI RADIAL OPTION
E-Multi User Manual