![Mitsubishi Electric MELSEC iQ-R-R00CPU User Manual Download Page 200](http://html.mh-extra.com/html/mitsubishi-electric/melsec-iq-r-r00cpu/melsec-iq-r-r00cpu_user-manual_239139200.webp)
198
11 DATA LOGGING FUNCTION
11.8 Data Logging File Transfer (Auto Transfer to FTP Server)
File transfer test
Check the communication status and settings by transferring a test file from the CPU module to the FTP server. The file
transfer to the FTP server can be checked before system operation.
■
Procedure for the file transfer test
The following describes the procedure for the file transfer test.
1.
Configure the transfer destination server setting in CPU Module Logging Configuration Tool. (
2.
Click the [File Transfer Test] button in the "FTP Setting" window to execute the file transfer test.
3.
Check the execution result.
4.
Check that the test file is transferred to the FTP server. (
Page 198 Structure of a test file)
■
Structure of a test file
The following table lists structures of a test file to be transferred to the FTP server.
■
File transfer test specification
• The FTP server connection request timeout time is fixed to 10 seconds.
• Even if the file transfer test fails due to a communication error, the retry is not executed.
• Even if the file transfer test fails, the error is not stored in the file transfer error history. (
■
Precautions
• File transfer tests cannot be executed simultaneously with another configuration tool. Execute the file transfer test after the
file transfer test from another configuration tool is completed.
• If the engineering tool is operated or monitored from the same connection destination of the same computer during the file
transfer test, the operation or monitoring will be executed after the file transfer test completion.
Item
Description
Example
Test file name
MELSEC_CPU_FTP_TEST_**.txt
** indicates the data logging setting number (two digits, with
zero-padding).
For setting No.1
MELSEC_CPU_FTP_TEST_01.txt
Contents of the test file
The IP address of the CPU module, test execution date,
and test execution time are described. For the date and
time, the clock data in the CPU module is used.
For IP address: 192.168.3.39, date: October 01, 2017, time:
11:22:33
192.168.3.39_20171001_112233
Summary of Contents for MELSEC iQ-R-R00CPU
Page 2: ......
Page 151: ...9 MONITOR FUNCTION 9 1 Real Time Monitor Function 149 9 MEMO ...
Page 323: ...18 SEQUENCE SCAN SYNCHRONIZATION SAMPLING FUNCTION 321 18 MEMO ...
Page 330: ...328 20 ROUTING SETTING 20 3 Precautions MEMO ...
Page 423: ...26 BASIC CONCEPT 26 8 State Transition of the Redundant System 421 26 MEMO ...
Page 1014: ...1012 APPX Appendix 15 Added and Enhanced Functions MEMO ...
Page 1027: ......