background image

 

 

BIO TURBO 300 

Toll Free in North America: 
1-800-933-6478 

www.miatech.org 

8AM-5PM PacificTime:

1-503-659-5680

June 2010

THE ADVANTAGE COUNTS

Description 
The BT-300 was designed to remove ethylene from 

cold rooms and storage areas where fruits and 

vegetables are stored, extending the life of the stored 

produce.  See picture 1.  System will handle 300 

cubic meters.  It is designed to hang from the ceiling 

and operate continuously. The BT-300 is also remote 

controlled for ease of operation. 
The air is first pulled into the Generation Chamber 

where it passes through a particle filter to remove any 

dust or foreign matter. The air then goes through a 

microbial filter. This filter will destroy 99.9% of the 

bacteria, fungi, mold, mildew, algae and other one 

celled organisms that cause odors, spoilage and rot. 
The air with ethylene then enters the ozone 

generation area where it mixes with ozone. The air 

mixed with ozone and ethylene then enters the 

Reaction Chamber where the ethylene will have 

contact time with the ozone. This is necessary to 

remove the ethylene from the air. 
After the ozone has removed the ethylene in the 

Reaction Chamber, the ozone enters the Catalytic 

Converter. Here, a special catalyst will deplete the 

remaining ozone. Clean air is then expelled through 

the controller. 

 
System Placement 

The Bio Turbo 300 was designed to mount as high as 

possible in the cold room. Ethylene is lighter than air 

so it will rise toward the ceiling. 

Note: Due to the size of the Bio Turbo system, 

installation is much easier with two technicians. 

 The large Reaction Chamber should be mounted 
first.  Inspect the ceiling for any obstructions, pipes 

and wiring before drilling any holes. Also consider an 

electrical receptacle to power the system.  Mark the 

two holes for the Reaction Chamber and drill the 

two 3/4 inch holes through the ceiling. Use the two 

8 inch bolts with wing nuts, self locking nuts and 
washers to attach the Reaction Chamber to the 

ceiling.  See picture 2

 

If supplied fasteners will not work for your 

installation, you will need to purchase necessary 
hardware locally. 

Next, mount the Generation Chamber to the 

Reaction  Chamber.  Ensure  the  gasket  is  in  place 

around the opening on the Generation Chamber. 

Use the four locking nuts that were supplied and 

attach the two chambers together. Only tighten 
these nuts SNUG (4 inch pounds). See picture 3. 

BIO TURBO 300 

INSTALLATION GUIDE v. 1.2 

 

Picture 1 

 

Picture 2 

 

Picture 3 

Reviews: