background image

P 9

Please retain product label and instructions for future reference

             

20

20

Step 14

Parts Needed - No. 20 QTY 34

Place the first floor board (

No. 20

)

inside the building flush to the log

board on one side. Continue adding

the floor boards (

internally

) making

sure to interlock each individual

board.

You have been issued with 35 floor 

boards, but in reality you may only 

need to use 34.

*Do 

NOT

 secure the boards until

the last board has been measured

and cut.

Following the same method outlined

previously measure the gap between

the bottom of the tongue (

on the last 

board placed

) and the log board.

Using a straight edge mark out the 

measurement onto the last floor

board (

No. 20

) and cut along the 

length removing the excess.

**Please note:

 Mark the final board

2mm under the measurement; This

will allow the timber to expand and

contract correctly.

Once all the floor boards are in 

position secure each board into

position using 8x40mm screws.

***Please Note:

 

Ensure to screw 

through each of the floor boards 

into the floor bearers.

272x40mm Screws 

40mm 

screw

Pre drill 

hole

*

Cut to fit

Closure Trim

Internal

23

*Measure and cut the

closure trims to

fit the internal space.

23

23

Closure Trim

Internal

12

*Measure and cut the

closure trims to

fit the internal space.

12

12

Pre drill 

hole

30mm 

screw

*

trim to fit

Step 15

Parts needed - No. 12 QTY 7 

   

 

Inside the building place the closure 

trim (

No. 12

) against the boarding 

and align with the roof as shown in 

the illustration.

Once in position fix each trim 

into place by pre drilling a pilot hole 

and using 6x30mm screws per trim, 

equally spacing them along the face 

of the board.

42x30mm Screws

30mm 

screw

Pre drill 

hole

*

Cut to fit

Step 16

Parts needed - No. 12 QTY 7 

Once the floor has been laid arrange the

closure trim (

No. 12)

 around the outside 

edge of floor (

internally

), measure and cut 

down accordingly to best match the 

internal space.

Secure each trim section into place using 

6x30mm spaced equally along the board 

as shown in the illustration.

*Do NOT fix the closure trim to the floor

boards.

42x30mm Screws

 

Roof

Roof

Summary of Contents for 0619LOG015-V5

Page 1: ...heltered as much as possible during rain or snow BUILDING A BASE When thinking about where the building and base are going to be constructed Ensure that there will be access 60cm to all sides for main...

Page 2: ...0x19x4000mm QTY 2 LB19RG50 A 4000 Log Board 120x19x2996mm QTY 25 LB19 A 2996 Log Board 120x19x1123mm QTY 24 LB19 B 1123 Roof Purlin 40x90x4004mm QTY 3 F4090 A 4004 Bearer 44x44x3720mm QTY 10 F4444 372...

Page 3: ...Felt Tacks x400 70mm Screw x64 Nail Bag 40mm Screw x506 30mm Screw x102 60mm Bolt Set x16 Pre assembly Please note Each board interlocks at either end in a staggered pattern Before securing ensure tha...

Page 4: ...14 14 14 14 14 14 14 IMPORTANT Pre drill before fixing screws Pre drill hole 70mm screw a Step 1 Parts Needed No 14 QTY 10 No 15 QTY 2 Lay the bearers No s 14 15 onto a firm and level surface free fro...

Page 5: ...boards are level and flush with each other as you lay each one Doors can be hung once the boarding has enclosed the door frame by 12 13 boards refer to door installation instructions if not you can in...

Page 6: ...other as you lay each one Doors can be hung once the boarding has enclosed the door frame Step 8 Parts Needed No 8 QTY 1 No 10 QTY 1 No 22 QTY 1 No 23 QTY 1 Following the same method outlined in Pre A...

Page 7: ...rts needed No 13 QTY 3 Align the Roof Purlin s No 13 into the cut out slots on each gable top ensuring each roof purlin interlocks the boards Secure the roof purlins at each end by screwing through th...

Page 8: ...at each board is interlocked flush at the bottom meet at the top of the apex The last board on each side will overhang Using a straight edge and a pencil mark out a line as a guide Cut along the penci...

Page 9: ...mm screws Please Note Ensure to screw through each of the floor boards into the floor bearers 272x40mm Screws 40mm screw Pre drill hole Cut to fit Closure Trim Internal 23 Measure and cut the closure...

Page 10: ...nging felt each side Once the felt is laid out fix to the roof using felt tacks at 100mm intervals Felt size 4124mm 252x Felt Tacks 1 2 3 4 Step 18 Parts Needed No 16 QTY 4 No 17 QTY 2 Align the fasci...

Page 11: ...ons for future reference Pre drill hole 60mm bolt Step 19 Parts needed No 21 QTY 8 Arrange the storm braces No 21 around the building internally Place 2x storm braces per side fixing into place using...

Reviews: