Step 2

Lay the door gable face up on a flat surface, place the door within the door aperture. Position the 

door so that you have a equal gap either side of the door to the gable. 

Once you are happy the door is in the correct position place a hinge at the top and bottom of the 

door, ensuring the screws will go into the framing (in cases where you have been supplied three 

hinges use the third in the middle of the door) and using 30mm black screws fix the hinge to the door 

and the door gable. Ensure to pre-drill the holes first. 

30mm Black Screw x 14

17

5

Lay the floor joists under 

the floor sheet with an even 

space between each one. 

Position the joists flush on 

one side of the floor sheet 

and mark the centers of 

joists onto either end . Fix 

using 4 x 30mm screws per 

joist.

30mm 

screw

Repeat the screws positions 

along each line

20 x 30mm Screws

Step 3

Place the floor on a firm 
and level base, ensure 
base has suitable 
drainage  free from areas 
where standing water can 
collect.  (See front page 
on base requirements).  

6

12

3 x 50mm screws

DO NOT SECURE THE BUILDING TO 

THE FLOOR UNTIL AFTER THE 

ROOF HAS BEEN FITTED.

Position the panels so there are 

equal gaps between the floor 

and cladding

Step 4

Fix the corners with 

3 x 50mm screws as in the 

diagram.

Attach the Plain Gable to the Left 

Window Side together with 3x50mm 

screws.

2

4

6

50mm 

screw

9 x 50mm screws

DO NOT SECURE THE BUILDING TO 

THE FLOOR UNTIL AFTER THE 

ROOF HAS BEEN FITTED.

Fix the corners with 

3 x 50mm screws as in the 

diagram.

Position the panels so there are 

equal gaps between the floor 

and cladding

Step 5

Attach the Door gable to the Right 

Window Side with 50mm screws.

1

3

50mm 

screw

Summary of Contents for 02RSE0505-V1

Page 1: ...lst all products manufactured are made to the highest standards of Safety and in the case of childrens products independently tested to EN71 level we cannot accept responsibility for your safety whilst erecting or using this product Mercia Garden Products Limited Sutton On Trent Newark Nottinghamshire NG23 6QN www merciagardenproducts co uk CAUTION Every effort has been made during the manufacturi...

Page 2: ... Hinge x2 10 12 Ridge Bar 28x28x1220mm Qty 1 Eaves Frame 28x28x1544mm Qty 2 Floor Joist 28x28x1210mm Qty 5 Fascia 40x12x790mm Qty 4 Finial Qty 2 Felt 16 11 13 15 17 18 Beading Block Qty 12 Cover Trims 40x12x1119mm Qty 2 14 Fascia Block 28x28x400mm Qty 1 19 20 21 Nail Bag 50mm Screw x28 40mm Screw x32 Felt Tacks x60 30mm Screw x64 60mm Screw x2 10mm Screw x4 30mm Black Screw x 16 Step 1 Remove tran...

Page 3: ... and mark the centers of joists onto either end Fix using 4 x 30mm screws per joist 30mm screw Repeat the screws positions along each line 20 x 30mm Screws Step 3 Place the floor on a firm and level base ensure base has suitable drainage free from areas where standing water can collect See front page on base requirements 6 12 3 x 50mm screws DO NOT SECURE THE BUILDING TO THE FLOOR UNTIL AFTER THE ...

Page 4: ...ews per eave Position the roof sheets on the building ensuring the roof sheet sits flush with the building at the back and fix using 10x40mm screws per sheet 30mm screw 7 11 7 14 x 50mm screws Fix the panels to the floor with 3x50mm screws per panel as in the diagram Position the panels so there are equal gaps between the floor and cladding Step 8 Fix the panels to the floor using 50mm screws as s...

Page 5: ... x 30mm screws 14 Step 10 14 Step 11 Cut the felt into 3 sheets at 1644mm and lay onto the roof as shown in the diagram ensuring there is a 50mm overhang around the sides Felt tacks 60 x felt tacks 21 Step 12 Fix the fascias and finials using 40mm screws Pre drill holes to avoid splitting Ensure to the trap the felt between the fascia and building 40mm screw 12 x 40mm screws 13 16 13 13 13 16 ...

Page 6: ...ws 8 9 20 24 x 30mm screws Step 14 Place the wooden door handle on the outside of door and use a 60mm screw from the inside to secure Pre drill hole first to avoid splitting Sandwich the door styrene between the door cut out and door flower then fix using 3 x 10mm screws Ensure the glazing covers the cut out and the screws do not crack the glazing Apply Clear Silicone Sealant not supplied around t...