Step 8

Parts needed -            &

 

Fix the 2x “L” brackets 

(No.19)

 to 

either end of the ridge bar

(No.17)

 using 

2x20mm screws per bracket.

*Ensure the bracket plate(

s

) are flush 

with each end of the ridge bar.

 

Once in place position the ridge bar

between the gable and window

panel, securing into position using

2x30mm screws per side. 

4x20mm Screws

4x30mm Screws

20mm 

screw

30mm 

screw

b

4

Step 5

Parts Needed -             & 

Place the left and right gable(

s

(

No’s. 3 & 4

) onto the floor (No.8) and 

fix together using 3x50mm 

screws. Ensure to secure through

the right gable into the panel

frame.

Do NOT secure the building to

the floor until after the roof has

been fitted.

3x50mm Screws

50mm 

screw

Please retain product label and instructions for future reference

             

Step 7

Parts needed -            &

Following the same method

outlined in 

Step 4

 fix the 

second window panel (

No. 2

and door panel (

No. 1

) into 

position, securing at the 

corner(

s

) with 3x50mm screws.

Do 

NOT

 secure the building to

the floor until after the roof has

been fitted.

9x50mm Screws

50mm 

screw

2

1

2

Step 6

Parts needed - 

Following the same method

outlined in 

Step 4

 fix the first 

window panel (

No. 2

) into 

position, securing at the 

corner with 3x50mm screws.

Do 

NOT

 secure the building to

the floor until after the roof has

been fitted.

3x50mm Screws

50mm 

screw

a

17

19

b

a

19

17

www.merciagardenproducts.co.uk      P5

DO NOT ALLOW YOUR CHILD TO PLAY WITH ANY 

COMPONENT PARTS PRIOR  TO ASSEMBLY.

1!

2!

Pre drill 

hole

1!

2!

Pre drill 

hole

1!

2!

Pre drill 

hole

1!

2!

Pre drill 

hole

3

Summary of Contents for 02CORPLAY0505-V1-PEFC

Page 1: ...y hard surface BUILDING A BASE Ensure the base is level and is built on firm ground to prevent distortion checking with a spirit level Refer to diagrams for the base dimensions The base should be slig...

Page 2: ...QTY x2 Roof OSB8 1492X1492mm 5 7 Floor AI 02CORPLAY0505 V1F Panel Frame 28x28x1240mm FS2828 1240mm Eaves Frame 28x28x884mm QTY x2 FS2828 884mm Eaves Frame 28x28x1436mm QTY x2 FS2828 1436mm Eaves Fram...

Page 3: ...oducts co uk P3 Pre Assembly Before assembling remove the transportation blocks from the bottom of each panel Take care removing the blocks as to not damage the panels Tap with a flat headed screwdriv...

Page 4: ...No 18 securing per hinge using 7x30mm black screws 21x30mm black screws 18 5 1 12mm 12mm 1 5 30mm screw 20 Step 2 Parts needed Position a window No 6 into each window panel No 2 and secure the window...

Page 5: ...x50mm Screws 50mm screw Please retain product label and instructions for future reference Step 7 Parts needed Following the same method outlined in Step 4 fix the second window panel No 2 and door pan...

Page 6: ...mes 16x30mm Screws 12 11 10 12 10 10 11 11 7 Step 10 Parts needed Place the assembled roof panel on top of the building and fix into position using 30mm screws Ensure to screw through the roof sheet i...

Page 7: ...felt to the roof using 78x felt tacks 78x Felt Tacks 22 HANDLE WITH CARE 1 2 3 4 Step 13 Parts needed Arrange the cover trims No 16 at front and side s of the building and fix into place using 3x30mm...

Page 8: ...erciagardenproducts co uk 1 2 Pre drill hole Playhouse Maintenance It is recommended that the following checks and maintenance are carried out at the begin ning of each season as well as at regular in...

Reviews: