background image

P 3

Please retain product label and instructions for future reference

             

Parts Needed - No. 1 Qty 1

 

 

   No. 4 Qty 2

 

 

   No. 14 Qty 4

Place the door gable 

(No. 1)

 on to a flat 

surface and place both doors

 (No. 4) 

into the door apeture. 

Locate the four t hinges 

(No. 14) 

onto 

the doors and door gable ensuring they 

sit over the door framing. Fix the hinges 

to the door and door gable using 

7x30mm screws per hinge.

28 x 30mm Screws

Step 1

1

4

14

30mm 

screw

Pre drill 

hole

IMPORTANT: 

Pre-drill before fixing screws.

Parts Needed - No. 6 Qty 2

Place the floors 

(No. 6)

 on a firm and 

level base, ensure the base has suitable 

drainage, free from areas where water 

can collect (see front page for base 

requirements).

Position the floors side by side as 

shown in the diagram. Fix together 

using 4 x 50mm screws alternating the 

fixing poisiton along the length of the 

floor.

5 x 50mm Screws

Step 2

Pre drill 

hole

50mm 

screw

6

6

IMPORTANT: 

Pre-drill before fixing screws.

Do not secure the building 

to the floor until the roof is 

fitted.

Fix the corner with 3x 

50mm screw a shown in 

diagram.

Step 3

IMPORTANT: 

Pre-drill before fixing screws.

Parts Needed - No. 2 Qty 1

 

 

   No. 3 Qty 1

3 x 50mm Screws

3

2

Pre drill 

hole

50mm 

screw

Do not secure the building 

to the floor until the roof is 

fitted.

Fix the corner with 3x 

50mm screw a shown in 

diagram.

Step 4

IMPORTANT: 

Pre-drill before fixing screws.

Parts Needed - No. 1 Qty 1

 

 

   No. 2 Qty 1

9 x 50mm Screws

1

2

Pre drill 

hole

50mm 

screw

Summary of Contents for 01OVEABKSTR-V4

Page 1: ...uired to maintain the anti rot guarantee Dip Treated buildings Require a preservative treatment to protect against rot and decay and a waterproof treat ment to prevent water ingress Pressure Treated b...

Page 2: ...loor Qty 2 AI 01OVEABKF795X990 V1 Fascia 7 x 60 x 1095mm Qty 4 OVLP760 1095MM Cover Trim 7 x 45 x 1324mm Qty 4 OVLP745 1324MM Eaves Frame 28 x 28 x 825mm Qty 2 F2828 825MM Ridge Bar 28 x 28 x 744mm Qt...

Page 3: ...as where water can collect see front page for base requirements Position the floors side by side as shown in the diagram Fix together using 4 x 50mm screws alternating the fixing poisiton along the le...

Page 4: ...per L Bracket 8 x 30mm Screws Pre drill hole 50mm screw 17 11 11 17 Step 6 IMPORTANT Pre drill before fixing screws Parts Needed No 5 Qty 2 No 10 Qty 2 Attach the Eaves Frame No 10 to the roof sheets...

Page 5: ...gable and the fascia Use 3 x 30mm screws per fascia ensuring to fix through to the panel framing behind Attach the finial No 13 to the fascias at the fornt and the back of the building using 2 x 30mm...

Page 6: ...screws 12 12 Step 12 Parts Needed No 16 Qty 4 Fix the turn buttons No 16 to the bolt blocks at the top and bottom of the door using a 30mm screw per turn button 2 x 30mm Screws 30mm screw Pre drill h...

Page 7: ...5 to the front of the doors fixing the staple to the doors with the turn buttons and the hasp to the opposing door securing into place with 5x30mm screws 5x 30mm Screws 30mm screw Pre drill hole IMPOR...

Reviews: