Step 11

Fix the pad bolt with 6x30mm 
screws to the horizontal brace 
on the door. Then fix the pad 
bolt retainer to the door panel 
framing using 4x30mm screws.

Fix the turn buttons using 
1x30mm black screw per turn 
button.

17

30mm 

screw

15

30mm 

screw

2x 30mm Black Screw

10x 30mm Screw

It is ESSENTIAL that you apply wood 

treatment immediately after the building 

has been assembled.

AFTER TREATMENT:

score around protective

 cover on glazing and

 carefuly peel

 covering back

Summary of Contents for 01OSBRA0604SDFW-V1

Page 1: ... Ensure that there will be access to all sides for maintenance work and annual treatment Whilst all products manufactured are made to the highest standards of Safety and in the case of childrens products independently tested to EN71 level we cannot accept responsibility for your safety whilst erecting or using this product Mercia Garden Products Limited Sutton On Trent Newark Nottinghamshire NG23 ...

Page 2: ... 10 Cover Trim 1800mm Qty 4 Ridge Bar 1707mm Qty 1 Door Strip 1590mm Qty 2 Eaves Frame 897mm Qty 4 Fascia 694mm Qty 4 Door Block 140mm Qty 1 Finial x2 T Hinge Qty 2 Felt L Bracket Qty 2 Turn Button Qty 2 Pad Bolt Qty 1 Nail Bag Felt Tacks x 63 20mm Screw x 12 30mm Black Screw x 2 30mm Screw x 68 50mm Screw x 26 40mm Screw x 36 Remove transportation blocks from the bottom of each panel before begin...

Page 3: ...ews as shown in diagram Position the panels so there is equal spacing between the floor and cladding on all 4 sides Step 2 2 3 3x50mm Screws Pre drill hole 50mm screw Step 3 9x50mm Screws Fix the corners with 50mm screws as shown in diagram Pre drill hole 50mm screw 1 3 Step 4 8x20mm Screws Place the ridge bar in between the two gables Ensure the top corners of the ridge bar sit flush with the top...

Page 4: ... through the roof sheet at the top Make sure to attach the roofs to the ridge bar 40mm screw Pre drill hole Pre drill hole 12x 30mm Screws 20x 40mm Screws Step 6 b Once the roof is fixed attach the building to the floor with 50 mm screws 14x 50mm Screws 50mm screw Pre drill hole 63x Tacks Felt tacks 18 18 18 Step 7 Cut the felt into two 1894mm long sheets and lay onto roof as shown in diagram ensu...

Page 5: ...light overhang at the top Fit the fascias to the roof over the felt and secure in place with 40mm screws as shown Pre drill to avoid splitting Pre drill hole 40mm screw 11 13 13 11 11 11 14 Step 10 Use 4x30mm screws to fix each beading strip onto the door panel Ensure that the screw is parallel with the door frame when fixing the strip to the door panel as shown in the close up view Line up the do...

Page 6: ...bolt retainer to the door panel framing using 4x30mm screws Fix the turn buttons using 1x30mm black screw per turn button 17 30mm screw 15 30mm screw 2x 30mm Black Screw 10x 30mm Screw It is ESSENTIAL that you apply wood treatment immediately after the building has been assembled AFTER TREATMENT score around protective cover on glazing and carefuly peel covering back ...

Reviews: