Planning example for installing the installation kit with a ductwork
connection in a frame construction with 160 mm thick framing members
Fig. 7: Planning example for installing the installation kit with a ductwork connection in a frame construction with
160 mm thick framing members
A- A
B- B
C
A
A
B
B
C
1
2
9
3
4
5
6
7
8
10
4
11
12
13
11
8
8
10
10
0
16
0
15
15
15
12
,5
31
7,
5
58
76
210
84
102
Cutouts in the
upper batten for
flat ductwork
Cutouts in the
lower batten for flat
ductwork
Option: M-WRG-II M/Fü
filler piece
Note the excess pipe length
specified in the installation man
-
ual for the outer wall terminals.
M-WRG-II ES: 5-10 mm
290 M-WRG-II
M
(shortened)
List of components
Item
Description
1
15 mm external render
2
Wood fibre insulation 100 mm
3
15 mm OSB board
4
160 x 60 mm framing member
5
160 mm insulation
6
15 mm OSB board
7
12.5 mm plasterboard
8
Batten (support and fixing for installation kit)
9
Outdoor air and exhaust air pipe DN 100
10
Installation kit M-WRG-II M
(option: M-WRG-II M/Fü filler piece)
11
M-WRG-II AD-UP ductwork connection adapter
12
M-WRG-FK-W flat ductwork elbow
13
M-WRG-FK-F flat ductwork 110 x 54 mm
Elbow shortened by