INSTALLATION
1) Install new pump gasket to cylinder block.
2) Install water pump (1) to cylinder block.
3) After installing water pump, install rubber seal (2) between wa-
ter pump and oil pump.
4) Install generator adjusting arm (1).
5) With engine oil applied to O-ring, install oil level gauge guide
(2).
6) Install timing belt tensioner plate, tensioner, tensioner spring,
timing belt and timing belt outside cover, referring to SECTION
6A.
7) Install crankshaft pulley, water pump pulley, pump drive belt.
8) Adjust water pump belt tension referring to SECTION 6H.
9) Connect negative cable at battery.
10) Fill cooling system.
11) After installation, check each part for leakage.
ENGINE COOLING
6B-13
SH410
REQUIRED SERVICE MATERIALS
MATERIALS
USE
Ethylene glycol base coolant
(Anti-freeze/Anti-corrosion coolant)
Additive to engine cooling system for improving cooling efficien-
cy and for protection against rusting.