POSITIONING
Units must be positioned on a firm, level stand that has been
bolted in place, or existing counter top, and bolted in place.
For mounting, these models are supplied with four threaded
bushings welded to the underside of the base.
The first installation step is to refer to the Specification
Sheets or Specification Drawings for detailed clearance
requirements and mounting hole locations of the kettle. If
you don’t have access to a specification sheet, check the
bottom of the kettle for location of threaded mounting
bushings.
CLEARANCE
REQUIREMENTS
* From back of mounting base.
Countertop Models
1.
Drill mounting holes. If mounting to a Cleveland stand
holes are already predrilled.
2.
Position the unit in its permanent location.
3.
Once positioned permanently secure the unit to the
mounting surface with the hardware provided.
4.
Seal around base of unit with silicone sealant.
5.
Remove protective material covering stainless steel
surfaces.
KET-20-T Leg Type Models
For floor type leg mount models position on a firm, level
sur face, level using adjustable feet and bolt two flanged
feet in place. Once the kettle is secure, screw tilt handle
into the threaded hole provided at the right of kettle.
ELECTRICAL
ENSURE THE ELECTRICAL SUPPLY MATCHES THE
KETTLE'S REQUIREMENTS AS STATED ON THE
RATING LABEL.
Install in accordance with local codes and/or the National
Electric Code ANSI/NFPA No. 70 (USA) or the Canadian
Electric Code CSA Standard C22.2 (Canada). A separate
fused disconnect switch must be supplied and installed.
The kettle must be electrically grounded by the installer.
Model #
Back* Left Right
Side
Side
KET-3-T
0
0
0
KET-6-T
6”
0
0
KET-12-T
6”
0
0
KET-20-T
9”
0
0
TKET-3-T
7 1/8”
0
0
TKET-6-T
7 1/8”
0
0
TKET-12-T
9 7/8”
0
0
A wiring diagram is affixed to the underside of the console
cover.
Remove the four screws securing the console cover and
remove the cover. Using a water tight fitting feed
permanent copper wiring through the cut-out in the rear or
bottom of the console, and fasten to the three connection
terminal block, which is mounted on the top of the
console’s control panel. Be sure to connect the ground
wire to the separate ground terminal connector (ground
lug). Replace console cover and secure it with the four
screws.
The kettle is wired for 3-phase operation at the factory. For
single phase operation, rewire the terminal block to that
shown in the above diagram
.
Note: Ensure main power is turned off before connecting
wires.
RED
YELLOW
BLACK
BLACK
BLUE
RED
L1 L2 L3
THREE
PHASE
RED
YELLOW
BLACK
BLACK
BLUE
RED
L1
L2
SINGLE
PHASE
ROUGE
JAUNE
NOIR
NOIR
BLEU
ROUGE
L1 L2 L3
TRI
PHASE
ROUGE
JAUNE
NOIR
NOIR
BLEU
ROUGE
L1
L2
MONO
PHASE
WATER FOR JACKET
The sealed jacket of the electric kettle is precharged with the
correct amount of a water based formula, and therefore, no
water connection is required to the kettle jacket.
FAUCET SPOUT
The kettle can be equipped with optional hot and/or cold water
faucet, requiring 1/2" copper tubing as supply lines. Mount
faucet bracket to the rear of the unt or studs provided.
Assemble faucet onto bracket and check for leaks.
POUR PATHS
Kettle Size
Min.
Max.
3 Gallon
15 1/2”
32”
6 Gallon
17 1/4”
36”
12 Gallon
18”
38”
20 Gallon
22”
45”
4.