Commissioning and operation
16
First commissioning
At the time of initial commissioning of a new or overhauled engine make sure to have ob-
served the “Technical Information for the installation of MAN Diesel engines”.
It is recommended that new or overhauled engines should not be operated at a load
higher than about 75% maximum load during the first few hours of operation. Initial run-in
should be at varying speeds. After this initial run-in, the engine should be brought up to
full output gradually.
Note:
Use only approved fuels, lubricants etc. (see brochure “Fuels, lubricants etc.”). Other-
wise the manufacturer’s warranty will become null and void.
Filling with fuel
Caution:
Fill the tank only when the engine is switched off. Pay attention to cleanliness.
Do not spill fuel.
Use only approved fuels, see brochure “Fuels, lubricants etc.”.
Filling-in of coolant
Fill the cooling system of the engine with a mixture of drinkable tap water and anti-freeze
agent on the ethylene glycole basis or anti-corrision agent.
See Publication “Fuels, Lubricants and Coolants for MAN Diesel Engines”.
D
Pour in coolant slowly via expansion tank, see page 27
Filling with engine oil
Caution:
Do not add so much engine oil that the oil level rises above the max. marking on the
dipstick. Overfilling will result in damage to the engine.
The engines are as a rule supplied without oil.
Pour oil into engine via filler neck, see page 21.
For the quantity required see “Technical Data”.
Summary of Contents for D 0824 LE 201
Page 1: ......
Page 2: ......
Page 3: ...3 Operating Instructions MAN Industrial Diesel Engines...
Page 4: ...4...
Page 14: ...Commissioning and operation 14 Engine views D 0824 LE 201 1 2 3 4 5 6 7 8 12 11 10 9...
Page 37: ......
Page 38: ......