7
SECTIONS OF THE BOILER
1. Control Panel
2. Top (cleaning) cover
3. Fan
4. Fuel Combustion Lid
5. Sifter
6. Stocker
7. Engine with Reductor
8. Stocker Fuel Disposal Lid
9. Circulation Flow
10. Safety Flow
11. Chimney Exhaust Pipe
12. Smoke Case
13. Circulation Return
14. Safety Return
15. Filling and Draining
4. INSTALLATION
*
Boiler must be installed evenly and must be placed on 10 cm high place in boiler room
installations.
*
Boiler must be connected to a good drawing chimney and minimum number of elbows
should be used between chimney and boiler.
*Boiler must be placed at a location with enough air intake for an efificient burning. It is required
to use open expansion tank for the installation of MAKTEK Automatic Coal Boilers.
* Boiler- expansion tank return pipes must be absolutely isolated in extreme cold regions.
* Warning line should be installed for taking the overflow water from the expansion tank.
*There shouldn't be any valves, check valves on the pipes between boiler expansion tank
*
Expansion tank volumes based on capacity are shown below: