4. Connect the input cables.
➢
R to INPUT L1,
➢
S to INPUT L2,
➢
T to INPUT L3,
➢
N (Neutral) to INPUT N.
5. Check the phase sequence.
6. Repeat steps 4-5 for output cables.
7. Replace the rear board and tighten the screws
Use the cable clips to stabilize the cables when the connections are done.
MAKE SURE THAT THE LOADS ARE İSOLATED FROM THE UPS OUTPUT İF
THEY ARE NOT READY TO BE CONNECTED.