215634
43
Revision B
ϭϬϯϴϬϯϮ
B
A
A
Figure 3.5: Lifting Plate
3.
If the windrower was lifted onto the assembly stands
using a crane:
Remove two bolts and nuts (A) attaching
lifting plate (B) to the walking beam. Discard the bolts, nuts,
and plate. Repeat this step for the lifting plate on the
opposite side of the walking beam.
ϭϬϯϴϬϯϬ
A
B
C
C
D
Figure 3.6: Supporting Fork Channel
4.
Support fork channel (A) with suitable lifting device (B), and
remove two bolts and nuts (C), and four washers (D), from
the walking beam. Discard the nuts, bolts, and washers.
1026715
A
B
Figure 3.7: Fork Channel
5.
At the side of the machine, remove bolt (A) and nut from
the forward end of fork channel (B). Discard the bolt
and nut.
6.
Ensuring that the fork channel does not snag on the hoses
and harnesses, move the fork channel away from the
windrower.
7.
Repeat Step
to Step
on the
opposite side.