6
1.
Clean walls and base
with brush and ensure
that there are no raised
obstructions that could
affect the final position of
the wall post.
2.
Confirm previously made
measurements of opening
widths.
3.
If top and bottom gaps
vary, take the smallest
size. You must ensure that
finished rails are totally
vertical.
4.
Place EPDM rubber
wall post sealing pad in
position so that wall post
will compress and seal to
the pad when fixed.
NOTE: The vertical D-seal is
supplied so that its position
is retained, so that it is longer
than the wall post. This is to
ensure that when the wall post
is positions onto the EPDM pad
the D seal will also seal into
the pad.
5.
Use packing shims
(normally for double
glazing) easily available
from builders merchants
- so if narrow at bottom,
pack out at top - if narrow
at top pack out at bottom.
Installation - Wall Rails (Face & Reveal)