Lucent Technologies 415B Battery Plant for 4ESS
Issue 6 September 1999
Introduction 1 - 1
1
Introduction
Product
Manual
This product manual (Select Code 167-792-121) describes the
installation, testing, operating, and maintenance instructions for
the 415B Battery Plant, which is shown in Figure 1-1. The
following list provides a reference key to the contents of this
product manual:
Section 1
Introduction
Section 2
System Description
Section 3
Safety
Section 4
System Installation
Section 5
System Testing
Section 6
Connecting Telecommunications Loads to
the Power Distribution Frame
Section 7
Retrofit of 415A Battery Plant
Section 8
Maintenance and Operation
Section 9
Glossary
415B Battery
Plant
The 415B Battery Plant contains the following subsystems:
•
KS-22089 AC Distribution Panel or Cabinet, two required;
also referred to as a Power Distribution Service Cabinet
(PDSC)
•
H569-429 Control and Distribution Bay; also referred to as
a Power Board
•
J87132B-2 140Vdc, 140A, 60Hz Ferroresonant Rectifier,
two to four required
•
J85501F-1 Galaxy Controller
•
J85568D-1 Power Distribution Frame (PDF), two required
•
KS-20472 Round Cell Batteries, 70 cells/string, up to three
strings
•
NE00305-45, G1 Enhanced Ground Current Monitor