a blunt chisel e.g. TX10 or H2.5 when resetting 

In the event of a repeated overheating, determine 

the cause of the fault and fix it before restarting. 

Before restarting the  boiler

• Check that the pump can rotate by turning 

the rotor with a screwdriver in the center 

hole of the pump.

• Check that the overheating protection is not 

tripped. Press the RESET-button (12) under 

the middle plastic screw with the red O-ring.

• Check that the boiler is water-filled and well 

vented.

Circulation Pump

For setting up the circulation pump, see separate 

instruction ”Grundfos UPM3 Auto 15/70”. Note 

that the pump is advantageously set to work with 

constant pressure and that this must be set manu-

ally according to separate instructions.

QR code for assembly instruction UPM3

Alarm codes

In the event of an operating problem then a fault 

code will be displayed as below.

Foult codes circulation pump

Display

Indication Operation

Action

Red LED, 

Yellow LED 

#5

Blocked 

rotor

False start 

was 1.33 s.

Wait or 

release rotor/

impellerr*

Red LED, 

Yellow LED 

#4

Too low 

voltage

Only one 

warning, the 

pump oper-

ates as normal

Check the 

voltage to the 

pump

Red LED, 

Yellow LED 

#3

Electric 

fault

Pump stops 

because of 

low voltage or 

serious fault

Check voltage 

to pump / Re-

place pump/

impeller

*

Release impeller using screwdriver PH2. Break the 

voltage to the pump. Insert the screwdriver into the 

center hole of the drive side, press the screwdriver in 

about 5 mm, then rotate forward /backward until the 
impeller loosens.

Installation

The boiler should be placed indoors/under a roof 

and fully protected from rain. The integrated 

safety package including automatic air-bleed 

valve, safety valve and connecting hoses, must 

be installed as shown in the product diagram (see 

above). Relevant building standards and hot wa-

ter installation standards must be adhered to. 

The safety valve’s outlet’s functioning must be 

ensured in the appropriate manner; refer to cur-

rent hot water installation standards. No thermo

-

meter is included in the standard kit. However, a 

thermometer should be mounted on the pipe after 

the boiler. The heating system must be arranged 

so that there is always a flow through the elec

-

trical cartridge. Check to see that one or more of 

the heating loops are always open.

Switching on

Before switching on, check to see that the hea-

ting system is filled with water, air-bled and that 

the system’s operating pressure is sufficient. 

Check to see that the circulation pump is run-

ning by listening to and testing the various pump 

speed settings.

Thermostat operation

Temperature regulation is via the boiler’s opera-

tional thermostat (constant output temperature). 

The thermostat can be set up to a maximum of 60 

ºC. Monitor the output temperature by means of 

a thermometer and compare it to the set tempera-

ture.

Overheating protection

Note!

Resetting is possible after the boiler has 

cooled down to approx. 65 ºC.

The boiler is provided with built in overheating 

protection, which cuts off the power at approx. 

80 ºC and att temperatures < −5 ºC.  To reset the 

overheating protection function, press the RE-

SET-button (12) 

under the middle plastic screw 

with the red O-ring

. Press the button hard with 

2 (3)