10
Indoor Unit
Installation
Flaring Work
Main cause for gas leakage is due to defect in flaring work. Carry out correct flaring work in the following proce-
dure.
Cutting the pipes and the cable.
1. Use the piping kit accessory or the pipes purchased
locally.
2. Measure the distance between the indoor and the out-
door unit.
3. Cut the pipes a little longer than measured distance.
4. Cut the cable 1.5m longer than the pipe length.
Removing burrs
1. Completely remove all burrs from the cut cross section
of pipe/tube.
2. Put the end of the copper tube/pipe in a downward
direction as you remove burrs in order to avoid dropping
burrs into the tubing.
Putting nut on
• Remove flare nuts attached to indoor and outdoor unit,
then put them on pipe/tube having completed burr
removal.
(not possible to put them on after flaring work)
Flaring work
1. Firmly hold copper pipe in a die in the dimension
shown in the table below.
2. Carry out flaring work wiht the flaring tool.
Copper
pipe
90
°
Slanted Uneven Rough
Pipe
Reamer
Point down
Flare nut
Copper tube
mm
inch
mm
Ø6.35
1/4
0~0.5
Ø9.52
3/8
0~0.5
Ø12.7
1/2
0~0.5
Ø15.88
5/8
0~1.0
Ø19.05
3/4
1.0~1.3
Outside diameter
A
Bar
Copper pipe
Clamp handle
Red arrow mark
Cone
Yoke
Handle
Bar
"A"