Commissioning
Before initial switch-on
36
Lenze · E84AYCEC communication module (POWERLINK) · EDS84AYCEC EN 4.0 - 02/2019
_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _
6
Commissioning
During commissioning, system-related data such as motor parameters, operating parameters, re-
sponses, and parameters for fieldbus communication are defined for the inverter. For Lenze devices,
this is done via the codes.
The codes of the inverter and communication are saved non-volatilely as a data set in the memory
module.
In addition, there are codes for diagnosing and monitoring the stations.
6.1
Before initial switch-on
Stop!
Before switching on the Inverter Drive 8400 and the communication module for the first
time, check the entire wiring for completeness, short circuit and earth fault.