Commissioning
Commissioning steps
EDK82ZAFPC-010 DE/EN/FR 6.0
64
H2_Inbetriebnahmeschritte-INB_E82ZAFPC001
Commissioning steps
Note!
Do not change the setting sequence.
Step-by-step commissioning of the function module with the DRIVECOM device control is
described below.
Step
Description
Detailed
information
1.
Configure master system (master) for communication with the
function module.
67
2.
Inhibit standard device via terminal 28 (CINH).
Set terminal 28 to LOW level.
Later the standard device can be inhibited and enabled via the
bus.
Documentation
of the standard
device
3.
Connect mains voltage and, if available, separate voltage supply of
the function module.
The standard device will be ready for operation after approx. 1
second.
Controller inhibit (CINH) is active.
69
Response
The green LED ”Connection status to the standard device” at the
front of the function module is lit (only visible in the case of 8200
vector).
Keypad:
(if plugged in)
70
4.
Activate bus terminating resistor via DIP switch = ONfor the first and
last node.
Lenze setting: OFF
68