NOTE: DIAGRAMS & ILLUSTRATIONS ARE NOT TO SCALE.

12

3. 

Cut or frame a hole through the outside wall 

for the installation of the air inlet hood.  A 
6-1/2" diameter hole is required.  Feed the 
loose end of the fl exible duct through the 
hole and attach to the collar on the air inlet 
hood using two (2) screws from the kit's 
hardware package.  Insert the hood into the 
opening.  Secure the inlet hood in place with 
nails driven through the holes in the fl ange.  
Seal with noncombustible waterproof silicon 
type caulking.

Steps 6 - Install Air Gate Kit 

(Required on All Indoor Instlaltions. When 
an Outside Air Kit is installed, see assembly 
steps on 

Page 6).

Install the Air Gate Kit per the instructions 
provided with kit and on 

Page 6

 (see

 

Page 23 

for ordering information).

Step 7.

  

Outside Air Kit (provided)

(Required on All Outdoor Instlaltions)

Install the Outside Air Kit per the instructions 
provided with kit and on 

Page 7

.

Step 8. 

Route the Class 0 metallic air duct per 

the instructions on 

Page 8

.

Step 9.

 Cut or frame a hole through the outside 

of the enclosure for the installation of the duct 
inlet hood per the instructions on 

Page 8

.

INSTALLING THE CHIMNEY SYSTEM

Step 1.

 Before continuing, check the operation 

of the damper, as described on 

Page 5

, (

refer 

to 

Figure 3

)

.

Step 2.

 Using standard construction framing 

techniques, construct opening for chimney route 
up through the ceiling(s) and roof or through 
an outside chase.

Framing must maintain adequate minimum air 
space clearance at all times.

Figure 28

A minimum 1"* air space must be reserved 
for clearance to insulation and construction 
materials extending for any continuous length 
surrounding the chimney.

*Note:

  

2" air space to insulation and construc-

tion materials required in Outdoor Installa-
tions when system height is less than 15 feet 
(see 

Table 2, Page 4).

In Canada, the chimney and outer wrapper 
require a minimum 2" air space to insulation 
and construction materials.

Reference 

Figures 19 & 20 

 and charts Framing 

Dimensions for Ceiling and Roof, which specify 
minimum ceiling and roof dimensions.

In new construction, to determine chimney center 
line, use plumb line from roof or ceiling above 
fi replace to center of fl ue collar on fi replace.

For remodeling, plumb to center of fl ue collar 
from ceiling above, drive nail through ceiling 
from below to mark position, then mark and 
cut to passage from above ceiling (around 
nail) (

see 

Figure 28

). 

Then plumb from ceiling 

or roof level directly above hole which has just 
been completed.

Firestop Spacer

Room Above

Firestop Spacer

Attic Above

Figure 29

Figure 30

Step 3.

 Position appropriate fi restop spacer 

at ceiling and nail temporarily with two (2) 8d 
nails. Use fl at fi restop spacer, Model F8FS, if 
chimney penetrates ceiling vertically. If chimney 
penetrates ceiling at 30° angle (offset chimney), 
use 30° fi restop spacer, Model F8FS30. Use one 
nail on opposite sides to hold fi restop spacer in 
position. Nail permanently, using at least two (2) 
more 8d nails, after chimney sections have been 
assembled through the fi restop spacer and after 
any necessary adjustments have been made. 
Firestop spacer must be secured by at least four 
(4) 8d nails when completely installed.

Notes:

 

Indoor Installations: 

 If there is a room above 

ceiling level, fi restop spacer must be installed 
on the bottom side of the ceiling. If an attic is 
above ceiling level, fi restop spacer must be 
installed on top side of ceiling joist (

Figures 

29 & 30

).

Outdoor Installations: 

 If patio installation 

requires that a chimney passes through a roof 
or room above, be sure to comply with all local 
building codes.

       CAUTION 

Allow minimum 1"* chimney air 
space to insulation and building 
materials throughout vertical or 
offset chimney installation.

       ATTENTION 

Permettez à minimum 1 pouce* 
espace aérien de cheminée à 
l’isolation, aux matériaux de 
construction et aux membres 
encadrants dans toute la verti-
cale ou excentrez l’installation 
de cheminée.

Summary of Contents for Merit Plus MP-420D

Page 1: ...EQUIPPED TO BE READILY IN STALLED OUTDOORS IF INSTALLED INDOORS YOU MUST INSTALL THE COMBUSTION AIR COVER PROVIDED WITH THE INSTALLATION KIT OR PURCHASE THE OPTIONAL OUTSIDE AIR KIT GATE OAKG OD SEE...

Page 2: ...tate and national codes and regulations 3 ThisfireplacemustbeinstalledwithSecurity Chimneys FTF8 8 203mm inside diam eter Chimney System only This fireplace is intendedforindoororoutdoorinstallations...

Page 3: ...always maintain minimum clearances to combustible materials and do not violate any specific installation requirements These fireplaces have been tested and listed by OMNI Test Laboratories Inc Report...

Page 4: ...materials Outdoor installations less than 15 height require chimney clearance of 2 air space to insulation and construction materials In Canada the chimney and fireplace outer wrapper require a minimu...

Page 5: ...kept within the shaded areas illustrated in Figure 7 CLEARANCES Minimum clearance to combustibles for the appliance is as follows sides and back 1 25 mm floor 0 0mm adjacentwall 12 305 mm ceiling 37 1...

Page 6: ...t If you plan to raise the fireplace and hearth extension build the platform assembly then position fireplace and hearth extension on top Secure the platform to the floor to prevent possible shifting...

Page 7: ...the outside air kit is NOT installed you must install the Outside Air Cover provided with the instructions kit b IfanoutsideairkitISinstalled theOutside Air Kit Gate must be installed see Page 23 of o...

Page 8: ...ons Outside Air Kit Installation provided These appliances are equipped with a com bustion air inlet collar so that it is possible to duct combustion air from the outdoors to the firebox To accomplish...

Page 9: ...g Materials if any Rough Framing Face Unfinished Shown Combustion Air Kit Optional Framing Dimensions A 46 1 2 1181 mm B1 43 1 2 1105 mm B2 60 1 2 1537 mm C 33 828 mm D 17 1 2 445 mm E 76 1 4 1937 mm...

Page 10: ...ions must not interfere with circulating grillwork Figure 19 Figure 20 A B Ceiling Framing C D Roof Framing Framing Dimensions for Ceiling Inches millimeters Flue Type A B FTF8 Vertical USA 14 1 2 368...

Page 11: ...les espaceurs du dessus du foyer voir le sch ma 13 ne peuvent tre retir es ou modifi es vous ne pouvez pas entaillez le colombage pour ajuster autour ou tre install plus bas que les espaceurs Le colom...

Page 12: ...and outer wrapper require a minimum 2 air space to insulation and construction materials Reference Figures 19 20 and charts Framing DimensionsforCeilingandRoof whichspecify minimum ceiling and roof di...

Page 13: ...e the building must be con structed with galvalume outer sections only Theappropriatemodeldesignationsarelocated in the back of this manual F8FS30 Firestop Spacer FTF8 S4 Stabilizer 1 Min Air Space 30...

Page 14: ...as noted in Step 4 Step 6 Select the proper Security Chimneys roof flashing based on pitch of roof Use chart below for selection Figure 37 Note Do not caulk or seal the ventilating open ings or seal t...

Page 15: ...chimney must be at least 2 above this reference point In all cases thechimneycannotbelessthen3 above the roof at the edge of the chimney The 2 in 10 rule is necessary in the interest of safety but doe...

Page 16: ...36 48 11 0 11 1 0 0 0 17 1 5 0 1 0 0 21 1 9 2 0 0 0 27 2 3 1 1 0 0 35 2 11 0 0 1 0 47 3 11 0 0 0 1 51 4 3 0 1 1 0 57 4 9 1 0 0 1 63 5 3 0 1 0 1 67 5 7 2 0 0 1 73 6 1 1 1 0 1 81 6 9 0 0 1 1 93 7 9 0 0...

Page 17: ...the Straight Up In stallation Instructions for cutting and framing ceiling and roof openings Note See Framing and Dimension Chart for the sizes of the ceiling and roof openings The size of the roof op...

Page 18: ...ilizer Considerthiswhen determining the need for a stabilizer Note Do not apply excessive pressure to any subsequent chimney section following return elbow assembly when installing Ensure that each su...

Page 19: ...c tions are placed lower than 18 inches from the fireplace opening These fireplaces have been marked with a maximum rating of 26 000 BTU to assure that homeowners do not exceed the allowable limits fo...

Page 20: ...ux non combustibles il se pourrait qu il n y ait pas suffisament de d gagement pour installer les portes de verre de votre choix Assurez d avoir un d gagmet suf fisant tout moment afin de ne pasinterf...

Page 21: ...es 416 x 1 Answer TheminimumrequiredthicknessoftheMicore160is 417 there fore round up to nearest standard thickness available which is 1 2 Using the r formula Note To convert inches to millimeters div...

Page 22: ...ormal wall decor with elaborate mantels to rustic wood paneling or warm brick facings Only noncombustible materials like stone tile brick etc may overlap the black front facing Do not extend these mat...

Page 23: ...ith fireplace Shownhereforre placement purposes only Locking Band 63L60 FLB Ref Form 750 080M Spark Arrester 63L57 FSA 2 Ref Form 750 198M INSTALLATION COMPONENTS The following items are available for...

Page 24: ...n For open top shrouds 96L20 FTF8 CTT Ref Form 750 077M Chimney Pack conventional Convenience Pack Residential 63L70 FTF8 CP7 Contains 3 FTF8 36 1 F8FS 1 F8F6 1 FTF8 CTD 7 P C 8 F T F R O I R E P U S...

Reviews: