Lennox HP27 SERIES Installation Instructions Manual Download Page 12

Page 12

WARNING

Danger of explosion:  Can cause equipment damage,
injury or death. When using a high pressure gas
such as dry nitrogen to pressurize a refrigeration or
air conditioning system, use a regulator that can
control the pressure down to 1 or 2 psig (6.9 to 13.8
kPa).

Using an Electronic Leak Detector or Halide

 1 − Connect a cylinder of HCFC-22 to the center port of the

manifold gauge set.

 2 − With both manifold valves closed, open the valve on

the HCFC-22 cylinder (vapor only).

 3 − Open the high pressure side of the manifold to allow

the HCFC-22 into the line set and indoor unit. Weigh in
a trace amount of HCFC-22.

 

[A trace amount is a maxi-

mum of 2 ounces (57 g) or 3 pounds (31 kPa) pres-
sure.]

 

Close the valve on the HCFC-22 cylinder and the

valve on the high pressure side of the manifold gauge
set. Disconnect the HCFC-22 cylinder.

 4 − Connect a cylinder of nitrogen with a pressure regulat-

ing valve to the center port of the manifold gauge set.

 5 − Connect the manifold gauge set high pressure hose to

the vapor valve service port. 

(Normally, the high pres-

sure hose is connected to the liquid line port; however,
connecting it to the vapor port better protects the man-
ifold gauge set from high pressure damage.)

 6 − Adjust the nitrogen pressure to 150 psig (1034 kPa).

Open the valve on the high side of the manifold gauge
set which will pressurize line set and indoor unit.

 7 − After a few minutes, open a refrigerant port to ensure

the refrigerant you added is adequate to be detected.
(Amounts of refrigerant will vary with line lengths.)
Check all joints for leaks. Purge nitrogen and HCFC-22
mixture. Correct any leaks and recheck.

Evacuation

Evacuating the system of noncondensables is critical for
proper operation of the unit. Noncondensables are defined
as any gas that will not condense under temperatures and
pressures present during operation of an air conditioning
system. Noncondensables and water vapor combine with
refrigerant to produce substances that corrode copper pip-
ing and compressor parts.

IMPORTANT

Use a thermocouple or thermistor electronic vacuum
gauge that is calibrated in microns. Use an instrument
that reads from 50 microns to at least 10,000 microns.

1 − Connect manifold gauge set to the service valve ports

as follows:
 

 

low pressure gauge to 

vapor 

service port

 

 

high pressure gauge to 

liquid 

line service valve

2 − Connect micron gauge.

3 − Connect the vacuum pump (with vacuum gauge) to the

center port of the manifold gauge set.

4 − Open both manifold valves and start the vacuum pump.

5 − Evacuate the line set and indoor unit to an 

absolute

pressure

 of 23,000 microns (29.01 inches of mercu-

ry). During the early stages of evacuation, it is desir-
able to close the manifold gauge valve at least once to
determine if there is a rapid rise in 

absolute pressure

.

A rapid rise in pressure indicates a relatively large leak.
If this occurs, repeat the leak testing procedure.

NOTE − The term absolute pressure means the total
actual pressure within a given volume or system,
above the absolute zero of pressure. Absolute pres-
sure in a vacuum is equal to atmospheric pressure mi-
nus vacuum pressure.

6 − When the absolute pressure reaches 23,000 microns

(29.01 inches of mercury), close the manifold gauge
valves, turn off the vacuum pump and disconnect the
manifold gauge center port hose from vacuum pump.
Attach the manifold center port hose to a nitrogen cylin-
der with pressure regulator set to 150 psig (1034 kPa)
and purge the hose. Open the manifold gauge valves
to break the vacuum in the line set and indoor unit.
Close the manifold gauge valves.

CAUTION

Danger of Equipment Damage.
Avoid deep vacuum operation. Do not use compres-
sors to evacuate a system.
Extremely low vacuums can cause internal arcing
and compressor failure.
Damage caused by deep vacuum operation will void
warranty.

7 − Shut off the nitrogen cylinder and remove the manifold

gauge hose from the cylinder. Open the manifold
gauge valves to release the nitrogen from the line set
and indoor unit.

8 − Reconnect the manifold gauge to the vacuum pump,

turn the pump on, and continue to evacuate the line set
and indoor unit until the absolute pressure does not
rise above 500 microns (29.9 inches of mercury) within
a 20−minute period after shutting off the vacuum pump
and closing the manifold gauge valves.

9 − When  the  absolute  pressure  requirement  above  has

been met, disconnect the manifold hose from the vacu-
um pump and connect it to an upright cylinder of
HCFC-22 refrigerant. Open the manifold gauge valves
to break the vacuum from 1 to 2 psig positive pressure in
the line set and indoor unit. Close manifold gauge
valves and shut off the HCFC-22 cylinder and remove
the manifold gauge set.

Summary of Contents for HP27 SERIES

Page 1: ...6 04 Supersedes 12 03 Table of Contents HP27 Outdoor Unit 1 Shipping Packing List 1 General Information 1 Unit Dimensions 2 Parts Arrangement 3 Setting the Unit 3 Electrical 4 Refrigerant Piping 6 Refrigerant Metering Device 10 Service Valves 10 Leak Testing 11 Evacuation 12 Start Up 13 Manifold Gauge Set 13 Charging 13 System Operation 15 Defrost System 16 Maintenance 17 HP27 Check Points 18 RETA...

Page 2: ...N OUTLETS Around perimeter of base 4 102 B 1 3 8 35 LIQUID LINE INLET 4 102 6 1 16 154 AIR INLET AIR A 4 7 8 22 4 1 2 114 2 9 16 65 2 51 2 51 13 5 8 473 26 5 8 676 7 1 2 191 7 1 2 191 3 7 8 98 3 7 8 98 28 1 8 714 32 1 8 816 34 1 16 865 Model No A B HS27 024 in 40 7 8 19 13 16 HS27 024 HP27 030 mm 1038 503 HP27 036 in 44 7 8 14 1 4 HP27 036 HP27 042 mm 1140 362 ...

Page 3: ... units must be maintained Refer to figure 2 for installation clearances 1 Place a sound absorbing material such as Isomode under the unit if you intend to install it in a location or a position that will transmit sound or vibration to the liv ing area or adjacent buildings 2 Install the unit high enough above ground or roof to prevent ice build up and to allow adequate drainage of defrost water 3 ...

Page 4: ...n per 5 foot 51 mm per 1 5 m slope tolerance away from building structure Slab Mounting ground level mounting slab building structure discharge air Figure 3 Roof Mounting If you are unable to mount the unit coil away from prevailing winter winds construct a wind barrier See figure 4 Size the barrier at least the same height and width as the out door unit Mount the barrier 24 inches 610 mm from the...

Page 5: ... for use only with copper conductors 24V Class II circuit connections are made in the low voltage junction box Refer to figure 5 for field wiring diagram NOTE A complete unit wiring diagram is located in side the unit control box cover 3 Install room thermostat ordered separately on an in side wall approximately in the center of the conditioned area and 5 feet 1 5 m from the floor It should not be...

Page 6: ...apor Line L15 Line Sets 024 030 3 8 in 9 5 mm 3 4 in 19 1 mm 3 8 in 9 5 mm 3 4 in 19 1 mm L15 41 15 ft 50 ft 4 6 m 15 2 m 036 042 3 8 in 9 5 mm 7 8 in 22 2 mm 3 8 in 9 5 mm 7 8 in 22 2 mm L15 41 15 ft 50 ft 4 6 m 15 2 m Installing Refrigerant Line During the installation of any heat pump or a c system it is important to properly isolate the refrigerant lines to prevent unnecessary vibration Line s...

Page 7: ...uid Line IMPORTANT Refrigerant lines must not contact structure Outside Wall Inside Wall Liquid Line Vapor Line IMPORTANT Refrigerant lines must not contact wall Wood Block Between Studs Strap Sleeve Wood Block Strap Sleeve Wire Tie Wire Tie Wire Tie NOTE Similar installation practices should be used if line set is to be installed on exterior of outside wall Figure 8 ...

Page 8: ...Wire Tie Wire Tie around vapor line only Floor Joist or Roof Rafter Tape or Wire Tie Strap the vapor line to the joist or rafter at 8 ft intervals then strap the liquid line to the vapor line To hang line set from joist or rafter use either metal strapping material or anchored heavy nylon wire ties Floor Joist or Roof Rafter Figure 9 ...

Page 9: ...ne Metal Sleeve Anchored Heavy Nylon Wire Tie Automotive Muffler Type Hanger Wall Stud Wall Stud Liquid Line Vapor Line Wrapped in Armaflex Strap Liquid Line To Vapor Line Metal Sleeve Figure 10 Outside Unit Placement and Installation Install unit away from windows Two 90 elbows installed in line set will reduce line set vibration Figure 11 ...

Page 10: ...n valves for use with specific match ups If you install a check expansion valve with an indoor coil that includes a fixed orifice remove the orifice before installing the check expansion valve IMPORTANT Failure to remove RFC orifice when installing an ex pansion valve on the indoor coil will result in improp er operation and damage to the system See figure 12 for installation of the check expansio...

Page 11: ...igure 14 The ball valve is equipped with a service port with a factory installed Schrader valve A service port cap protects the Schrader valve from contamination and assures a leak free seal Vapor Line Service Valve Valve Open Schrader valve stem cap To open rotate stem counter clockwise 90 To close use adjustable wrench and rotate stem clockwise 90 ball shown open service port cap service port fi...

Page 12: ...as follows low pressure gauge to vapor service port high pressure gauge to liquid line service valve 2 Connect micron gauge 3 Connect the vacuum pump with vacuum gauge to the center port of the manifold gauge set 4 Open both manifold valves and start the vacuum pump 5 Evacuate the line set and indoor unit to an absolute pressure of 23 000 microns 29 01 inches of mercu ry During the early stages of...

Page 13: ...act this amount The outdoor unit should be charged during warm weather However applications arise in which charging must occur in the colder months The method of charging is deter mined by the unit s refrigerant metering device and the out door ambient temperature Measure the liquid line temperature and the outdoor ambi ent temperature as outlined below 1 Close manifold gauge set valves Connect ma...

Page 14: ...hile charging 1 Record outdoor ambient temperature using a digital thermometer 2 Attach high pressure gauge set and operate unit for several minutes to allow system pressures to stabilize 3 Compare stabilized pressures with those provided in table 6 Normal Operating Pressures Minor varia tions in these pressures may be expected due to differ ences in installations Significant differences could mea...

Page 15: ...TOR System Operation The outdoor unit and indoor blower cycle on demand from the room thermostat When the thermostat blower switch is in the ON position the indoor blower operates continuously CAUTION Danger of Equipment Damage Do not bypass the discharge thermostat Filter Drier The drier is equipped with an internal check valve for correct refrigerant flow Refer to figure 16 If replacement is nec...

Page 16: ...laced across the TEST pins for two seconds the control will enter the defrost mode If the jumper is removed before an addi tional 5 second period has elapsed 7 seconds total the unit will remain in defrost mode until the defrost thermostat opens or 14 minutes have passed If the jumper is not re moved until after the additional 5 second period has elapsed the defrost will terminate and the test opt...

Page 17: ...ice or maintenance turn the electrical power to unit OFF at dis connect switch es Unit may have multiple power supplies Maintenance and service must be performed by a qualified installer or service agency At the beginning of each cooling or heating season the system should be checked as fol lows Outdoor Unit 1 Clean and inspect outdoor coil may be flushed with a water hose Ensure power is off befo...

Page 18: ...ompressor Monitor Compressor Crankcase Heater Hail Guards Mounting Bases Timed Off Control Stand off Kit Sound Cover Low Ambient Kit Monitor Kit HP27 Check Points Start up and Performance Check List Job Name Job Location Installer Unit Model No Nameplate Voltage Rated Load Ampacity Maximum Fuse or Circuit Breaker Refrigerant Lines Service Valves Fully Opened Outdoor Fan Checked Job No City City Se...

Reviews: