Page 20

Evacuating Line Set and Indoor Coil 

A

Open both manifold valves and start the vacuum pump.

B

Evacuate the line set and indoor unit to an 

absolute pressure

 of 23,000 microns (29.01 inches of mercury).

NOTE 

— During the early stages of evacuation, it is desirable to close the manifold gauge valve at least once. A rapid rise in pressure

indicates a relatively large leak. If this occurs, 

repeat the leak testing procedure

.

NOTE 

— The term 

absolute pressure

 means the total actual pressure within a given volume or system, above the absolute zero of

pressure. Absolute pressure in a vacuum is equal to atmospheric pressure minus vacuum pressure.

C

When the absolute pressure reaches 23,000 microns (29.01 inches of mercury), perform the following:

Close manifold gauge valves

Close valve on vacuum pump

Turn off vacuum pump

Disconnect manifold gauge center port hose from vacuum pump

Attach manifold center port hose to a dry nitrogen cylinder with pressure regulator set to 150 psig (1034 kPa) and purge the hose.

Open manifold gauge valves to break the vacuum in the line set and indoor unit.

Close manifold gauge valves.

D

Shut off the dry nitrogen cylinder and remove the manifold gauge hose from the cylinder. Open the manifold gauge valves to release the

dry nitrogen from the line set and indoor unit.

E

Reconnect the manifold gauge to the vacuum pump, turn the pump on, and continue to evacuate the line set and indoor unit until the

absolute pressure does not rise above 500 microns (29.9 inches of mercury) within a 20-minute period after shutting off the vacuum pump
and closing the manifold gauge valves.

F

When the absolute pressure requirement above has been met, disconnect the manifold hose from the vacuum pump and connect it to an

upright cylinder of HFC-410A refrigerant. Open the manifold gauge valve 1 to 2 psig in order to release the vacuum in the line set and
indoor unit.

G

Perform the following:

OUTDOOR

UNIT

TO VAPOR

SERVICE VALVE

TO LIQUID LINE
SERVICE VALVE

MICRON

GAUGE

VACUUM PUMP

A34000 1/4 SAE TEE WITH
SWIVEL COUPLER

500

MANIFOLD

GAUGE SET

HFC-410A

RECOMMEND

MINIMUM 3/8” HOSE

A

Connect low side of manifold gauge set
with 1/4 SAE in-line tee to 

vapor 

line

service valve

B

Connect high side of manifold gauge
set to 

liquid 

line service valve

C

Connect micron gauge available
connector on the 1/4 SAE in-line tee.

D

Connect the vacuum pump (with
vacuum gauge) to the center port of the
manifold gauge set. The center port
line will be used later for both the
HFC-410A and nitrogen containers.

HIGH

LOW

1

2

3

4

5

6

7

8

9

10

11

12

1/6 TURN

NITROGEN

1

CONNECT GAUGE SET

A

B

C

D

2

EVACUATE THE SYSTEM

NOTE 

— Remove cores from service valves (if not already done).

Close manifold gauge valves.

Shut off HFC-410A cylinder.

Reinstall service valve cores by removing manifold hose from service valve. Quickly install cores with core
tool while maintaining a positive system pressure.

Replace stem caps and secure finger tight, then tighten an additional one-sixth (1/6) of a turn as illustrated.

Figure 12. Evacuating System

Summary of Contents for EL16XC1 Series

Page 1: ...multiple power supplies TABLE OF CONTENTS Model Number Identification 2 Typical Serial Number Identification 2 Specifications 2 Electrical Data 3 Unit Dimensions 4 Unit Parts Arrangement 5 Operating...

Page 2: ...de 08 2008 09 2009 10 2010 Month Code A January B February C March 05716 5 or 6 Digit Unique Number Location Code 19 Saltillo Mexico 58 Marshalltown IA 5 Specifications Model Numbers Unit Outdoor Fan...

Page 3: ...C1 024 25 14 6 10 9 59 3 1 6 825 1 0 1 9 EL16XC1 030 25 17 0 12 8 67 8 1 6 825 1 0 1 9 EL16XC1 036 EL16XC1S036 30 18 0 13 6 79 0 1 6 825 1 0 1 9 EL16XC1 041 30 19 3 14 7 75 0 1 6 825 1 0 1 9 EL16XC1 0...

Page 4: ...6XC1 030 39 991 30 1 2 775 35 889 13 7 8 352 7 3 4 197 3 1 4 83 27 1 8 689 3 5 8 92 4 1 2 114 20 5 8 524 EL16XC1 036 EL16XC1S036 31 787 30 1 2 775 35 889 13 7 8 352 7 3 4 197 3 1 4 83 27 1 8 689 3 5 8...

Page 5: ...K1 1 CAPACITOR C12 CONTROL PANEL TYPICAL PLUMBING COPELAND COMPRESSOR DISCHARGE LINE HIGH TEMPERATURE SENSOR LIQUID LINE FILTER DRIER SINGLE FLOW DISCHARGE LINE HIGH TEMPERATURE SENSOR COMPRESSOR HARN...

Page 6: ...risks rounding or breaking off the wrench or stripping the valve stem recess See the Lennox Service and Application Notes C 08 1 for further details and information IMPORTANT To prevent stripping of t...

Page 7: ...6 7 8 9 10 11 12 1 12 TURN To Access Service Port A service port cap protects the service port core from contamination and serves as the primary leak seal 1 Remove service port cap with an appropriat...

Page 8: ...e unit s sound level registered from the adjacent property not from the installation property Install the unit as far as possible from the property line When possible do not install the unit directly...

Page 9: ...f two 2 degrees or two inches per five feet 50 mm per 1 5 m away from building structure MOUNTING SLAB BUILDING STRUCTURE GROUND LEVEL Outside Unit Placement Slab Mounting at Ground Level SAME FASTENE...

Page 10: ...n the direction of prevailing winds NOTICE Roof Damage This system contains both refrigerant and oil Some rubber roofing material may absorb oil and cause the rubber to swell when it comes into contac...

Page 11: ...E AS CLOSE TO PARALLEL WITH THE UNIT AS POSSIBLE WHILE INSTALLING PANEL PREFERRED ANGLE FOR INSTALLATION ANGLE MAY BE TOO EXTREME HOLD DOOR FIRMLY TO THE HINGED SIDE TO MAINTAIN FULLY ENGAGED TABS Det...

Page 12: ...g torch while pressurized may result in ignition of the refrigerant and oil mixture check the high and low pressures before unbrazing WARNING When using a high pressure gas such as dry nitrogen to pre...

Page 13: ...OR RAFTER AT 8 FEET 2 43 METERS INTERVALS THEN STRAP THE LIQUID LINE TO THE VAPOR LINE FLOOR JOIST OR ROOF RAFTER REFRIGERANT LINE SET INSTALLING HORIZONTAL RUNS NOTE Similar installation practices sh...

Page 14: ...operations only in well ventilated areas Wear gloves and protective goggles or face shield to protect against burns Wash hands with soap and water after handling brazing alloys and flux IMPORTANT Con...

Page 15: ...Y FROM SERVICE VALVE Flow regulated nitrogen at 1 to 2 psig through the low side refrigeration gauge set into the liquid line service port valve and out of the suction vapor line service port valve CU...

Page 16: ...ions for the next step in preparing the unit WHEN BRAZING LINE SET TO SERVICE VALVES POINT FLAME AWAY FROM SERVICE VALVE PREPARATION FOR NEXT STEP 7 WARNING 1 FIRE PERSONAL INJURY OR PROPERTY DAMAGE w...

Page 17: ...the liquid line to the indoor unit s liquid line orifice housing LOW HIGH EXISTING INDOOR UNIT GAUGE MANIFOLD INVERTED HCFC 22 CYLINDER CONTAINS CLEAN HCFC 22 TO BE USED FOR FLUSHING LIQUID LINE SERV...

Page 18: ...EMBLY WITH BRASS NUT DISTRIBUTOR ASSEMBLY A Remove the field provided fitting that temporary reconnected the liquid line to the indoor unit s distributor assembly B Install one of the provided Teflon...

Page 19: ...inder of HFC 410A refrigerant to the center port of the manifold gauge set Open the valve on the HFC 410A cylinder vapor only B Open the high pressure side of the manifold to allow HFC 410A into the l...

Page 20: ...oor unit until the absolute pressure does not rise above 500 microns 29 9 inches of mercury within a 20 minute period after shutting off the vacuum pump and closing the manifold gauge valves F When th...

Page 21: ...diagrams and refer to unit nameplate for minimum circuit ampacity and maximum overcurrent protection size 24VAC TRANSFORMER Use the transformer provided with the furnace or air handler for low voltage...

Page 22: ...PERATURE RATING MORE THAN 100 30 METERS 16 35 C MINIMUM WIRE NUTS BLACK 24V CONTROL WIRES YELLOW TIGHTEN WIRE TIE UNIT LOW VOLTAGE CONNECTIONS NOTE DO NOT BUNDLE ANY EXCESS 24VAC CONTROL WIRES INSIDE...

Page 23: ...cessary 6 Inspect contactor contacts for pitting or burn marks Replace as necessary 7 Check outdoor fan motor for worn bearings bushings Replace as necessary 8 Inspect and clean outdoor coils if neces...

Page 24: ...m Fuse or Circuit Breaker Electrical Connections Tight Indoor Filter clean Supply Voltage Unit Off Indoor Blower RPM S P Drop Over Indoor Dry Outdoor Coil Entering Air Temp Discharge Pressure Suction...

Page 25: ...Page 25 EL16XC1 SERIES Typical Field Wiring...

Page 26: ...Page 26 Typical Factory Wiring...

Page 27: ...supply at the disconnect switch The voltage must be within the range listed on the unit s nameplate If not do not start the equipment until you have consulted with the power company and the voltage co...

Page 28: ...mperature of air entering indoor coil F INDOOR COIL DRY BULB DRY BULB WET BULB B TDrop 19 A Dry bulb Wet bulb F A 72 B 64 C 53 air flow air flow All temperatures are expressed in F 1 Determine the des...

Page 29: ...t 4 6 m line set 3 8 9 5 mm 3 ounce per 5 85 g per 1 5 m If line length is greater than 15 ft 4 6 m add this amount If line length is less than 15 ft 4 6 m subtract this amount Refrigerant Charge per...

Page 30: ...OOR COIL sometimes necessary with lower temperatures Use cardboard or plastic sheet to restrict the airflow through the outdoor coil to achieve pressures from 325 375 psig 2240 2585kPa Higher pressure...

Page 31: ...than shown then REMOVE refrigerant If refrigerant is REMOVED retest to confirm that unit is properly charged MORE or LESS If refrigerant is ADDED retest to confirm that unit is properly charged ABOVE...