Page 11 of 11
STEP 12
STARTING THE CHARGE CONTROLLER
STEP 13
END OF INSTALLATION AND START-UP
YOUR PIVO LEKLA MULTI-PURPOSE AUTONOMOUS ENERGY STATION IS NOW FUNCTIONAL.
Connect the cables to the controller in the following order:
The connectors of the red/black wire pair on the batteries, the orange/black wire pair on Load 1 and/or Load 2
according to the identification label and the yellow/black wire pair on Solar 1.
In the event of a disconnection, please proceed in the reverse order.
If everything is working correctly, the green battery LED indicator and the Solar 1 LED indicator will light up.
The diagram below displays and identifies all the LED indicators.
At this stage, the PIVO | LEKLA should be functional. It will be possible to remotely perform a variety of tests and
to generate management reports from the ILLUMIENCE web site of ClearBlue technologies.
In case of problems, contact the LEKLA service center at 819-769-0350