Floor level difference should not exceed 10cm.
Installation standard
A. Frame section standard:
1. Adjust the height of the column according to site floor, ensure columns at the same level.
2.
Ensure columns vertically during frames mounting, The column tilt up and down not more than
10mm.
3. Do frame diagonal measurement during installation,comparative data is not more than 10mm.
4. After frame installation completed, make sure the two rails are in same level and In parallel,
distance between two rails is 3305mm.
B. Waterway, circuit part standard:
1. Take reference to frames when mounting the high pressure water hose, make sure high
pressure hose freely bended and not in force.
2. Insert rubber cushion between waterway galvanized tube with frame and ground for damping