Load not operating properly 

 
1.  Press the TEST button to turn the lights on. This will assist in troubleshooting 

the problem. 

2.  Check that the load is turned on. Check that no system fuses are defective. 

Check that no system circuit breakers are tripped.  Remember that there are 
no fuses or circuit breakers inside the SunLight. 

3.  Check connections to the load, and other controller and battery connections. 

Make sure voltage drops in the system wires are not too high. 

4.  Check for proper LED indications on the SunLight. If the red LOAD DISCON-

NECT LED is on, the load has been disconnected due to low battery voltage. 

This is generally a normal state when the load exceeds the PV array output 
due to weather and other sunlight conditions. 

5.  Check the PV array voltage under direct sun, with the array leads disconnect-

ed. The voltage should be close to the expected open circuit voltage for the 
panel type used. 

6.  Visually inspect the PV array and verify that the array is clear of debris (e.g. 

leaves, snow, dirt) and that it is oriented correctly for the installation location. 

7.  Measure the voltage at the controller BATTERY terminals. If this voltage is 

above the LVD, the load should have power. Press the test button and then 
measure the voltage at the controller LOAD terminals, and if there is no volt-
age present, the controller may be defective. 

Kaleidoscope® smart shelter installation and maintenance manual

 

troubleshooting 

Summary of Contents for Kaleidoscope smart

Page 1: ...Kaleidoscope smart shelter transit shelter solar lighting system installation and maintenance manual September 6 2017...

Page 2: ...sed of three 12 Volt batteries The batteries are sealed lead acid rechargeable with excellent temperature performance and very long life Luminaires The LED luminaires contain high power warm white LED...

Page 3: ...roof panel Be careful not to wrinkle the panel or trap air underneath it This process may be easier with two people Note At this point the solar panel and the power unit should be mounted to the shelt...

Page 4: ...e Black wire from luminaire 2 to the Black wire of the LED driver All electrical connections are complete at this point 9 Switch the battery disconnect to the On position 10 Before re installing power...

Page 5: ...d direct spray into drain holes on power module lid The main housing has several drain holes Ensure that they are free of debris Visual inspection check over exterior assembly for cracks missing or br...

Page 6: ...before sunrise require that the SunLight measure the length of the night Therefore the controller cannot turn the lights on before sunrise the first night after installation or after reconnect ing th...

Page 7: ...ected due to low battery voltage This is generally a normal state when the load exceeds the PV array output due to weather and other sunlight conditions 5 Check the PV array voltage under direct sun w...

Page 8: ...0 521 2546 F 269 381 3455 www landscapeforms com Note The 4 post unit uses one 2 post system and one 3 post system Kaleidoscope smart shelter installation and maintenance manual mechanical installatio...

Page 9: ...ms Inc Printed in U S A OUR PURPOSE IS TO ENRICH OUTDOOR SPACES We believe in the power of design and its ability to influence and elevate the quality of public space High quality products and outstan...

Reviews: