3 operaTionaL seTTings
1. Position the cooling unit horizontally and keep obstructions away from the air inlet to allow
for sufficient air circulation.
2. Remove the reservoir cap.
3. Connect the external hoses supplied by the user.
4. Insert the cable and connect the cable to the terminals according to the terminal diagram;
use a 3 mm screwdriver to connect the wires to the terminal block.
5. Fill the cooling unit with approximately 3.7 L of coolant.
Note:
The coolant level must be approximately 3 cm above the fins to maintain peak
cooling performance, otherwise the cooling capacity will be reduced.
6. Allow the cooling unit to run for 10 minutes and deaerate the liquid circuit.
7. Check the coolant level and refill if necessary.
8. Close the reservoir cap.
User