6 Initial Operation
6.1 Safety Indications Related to Initial Operation
CAUTION
Danger of malfunction caused by faulty connections during initial operation!
Before switching on the unit make sure that:
All safety equipment of the unit is implemented and functional.
All connections were properly made.
Please follow the rules in chapter Safety Regulations on page 9.
6.2 Setting to Work
6.2.1 Placement
Fig. 7:
Minimum clearance for air entrance and air exit
1)
Move the unit to its installation location as mentioned in chapter 5.2.
2)
Place the unit in a way that air entrance and air exit are not obstructed. Wall clearance on the left side
(facing the unit) must not be less than 0,5 m, otherwise operating capacity may be restricted
PLEASE NOTE
In case of storage of the unit at temperatures lower than 5°C or higher than 40°C for longer periods please
wait 3 hours prior to initial operation to allow for temperature adjustment.
0.5 m min.
Air intake for
the motor