Maintenance
91
Control Circuit
The control circuit allows maintenance personnel to check and adjust the system pressure at different
points along the circuit. The following items can be checked and adjusted:
Standby pressure
Arm pump pressure
Packer pump pressure
Adjusting Standby Pressure
To adjust the standby pressure, proceed this way:
1.
INSERT a 0-3000
psi gauge into the P2 port (see Figure 3-65).
2.
With the pump on and no functions operating, SET pressure to 250
psi by turning the
adjustment capscrew clockwise or counter-clockwise depending on the gauge reading
(see Figure 3-65).
3.
REMOVE the gauge after correctly setting the pressure.
Figure 3-65 Standby pressure adjustment
Adjusting Arm Pump Pressure
To adjust the arm pump pressure:
1.
INSERT a 0-3000
psi gauge into the P2 port (see Figure 3-66).
2.
With the pump on and the arm function stroked to the full up position, SET pressure to 3000
psi
by turning the adjustment capscrew clockwise or counter-clockwise depending on the gauge
reading (see Figure 3-66).
3.
REMOVE the gauge after correctly setting the pressure.
P2 Port
Adjustment
capscrew
Summary of Contents for ALLEY -GATOR RIGHT-HAND
Page 1: ...ALLEY GATOR RIGHT HANDTM MAINTENANCE MANUAL...
Page 2: ......
Page 3: ...ALLEY GATOR RIGHT HANDTM MAINTENANCE MANUAL...
Page 5: ......
Page 6: ......
Page 10: ...viii Table of Contents...
Page 16: ...6 Introduction...
Page 38: ...28 Safety...
Page 104: ...94 Maintenance Figure 3 69 Packer choke valve w cap w o cap Adjustment screw Valve with cap...
Page 107: ......