5. SWITCHING ON THE MACHINE
5.1 FILLING THE BOILER
A. Open the water supply tap as arranged during the preparatory stages (see Fig. 12 on page 20 - Ref. 1).
B. Verify that the water mains pressure (approx. 4 bar) is visualized on the water mains pressure gauge (14).
C. Push the manual filling valve on the appliance (19) until the boiler level indicator is halfway (16).
5.2 SWITCHING ON THE APPLIANCE
A. Turn on the power supply switch that was prearranged during the system preparation (see Fig. 11 page 18 – Ref. 1), and then turn
on the machine’s main switch (
12).
Once the machine is switched on, an electronic components check is carried through on 2-3-4 groups machines; all the symbols on
the control panel, from left to right, are progressively turned on. At the end of this process, the symbol for the temperature setting
will start to blink to indicate that the appliance is heating up.
Take note!
According to the amount of water filled manually, it is possible to activate the automatic refill system when the switch (
12) is
turned on, until the boiler water level indicated by the manufacturer is reached.
Summary of Contents for Compact S8
Page 51: ...espresso coffee machines 49 8 9 LSI 089 Rev 00 Ed 04 2015 DIAGRAMS...
Page 56: ...espresso coffee machines 54 8 9 LSI 089 Rev 00 Ed 04 2015 9 WIRING DIAGRAMS...
Page 57: ...espresso coffee machines 55 8 9 LSI 089 Rev 00 Ed 04 2015 9 1 S8 S9 COMPACT WIRING DIAGRAMS...
Page 61: ...espresso coffee machines 59 8 9 LSI 089 Rev 00 Ed 04 2015...
Page 62: ...espresso coffee machines 60 8 9 LSI 089 Rev 00 Ed 04 2015...
Page 63: ......