background image

Placing of the equipment and foundation:

1

Dig holes as displayed in figure 2. Place 80mm of compressed gravel into all four holes. 

2

Place the equipment into the holes as figure 2 displays. The surface signage on the posts 
should be at surface level.

3

Caution: The timber shall not have contact to the ground soil.

4

Place approximately 1/4th of the amount of concrete into each hole. Make sure the concrete 
is at least 400mm below ground surface.

5

Fill up with gravel and make sure to leave space for the fall protection surface.

6

Caution: when using different types of fall protection be certain that it fulfills all safety 
requirements as described on next page.

7

Caution: The swings must have a minimum ground clearance of 360mm.

Figure 2 displays the holes for the ground fasteners. All measurements are in mm.

Reviews: