 The power of the electric heater must correspond to the size of the steam room.
The steam room should be at least 1.9 m high.
The sauna should have natural ventilation. Air intake and exhaust should be located diagonally at the 
top and bottom of the heated room, but not in the corner where the electric heater is placed.
The temperature sensor must be connected to the switching unit using the wires supplied in the de-
livery package. The electric heater must be connected to the switching unit using appropriately sized 
heat-resistant insulated wires (see Table 2).
Before installing the control unit, check its integrity and completeness, and make sure the model of 
the control unit selected is appropriate for the electric heater model.
The length of connecting wires shall be as follows:
- Control cable (4) from switching unit to control unit - 5 m
- Temperature sensor wire (3) from switching unit to temperature sensor - 5 m
The control unit's wiring diagram is shown in Fig. 1d.

CAUTION! 

Before starting the wiring, make sure the power supply to which the electric heater and 

the control unit are connected is de-energised.
The control box shall be installed outside of the steam room. To mount the control box, drive impact 
anchors with a diameter of 4 mm (not included in the delivery package) into the wall in one horizon-
tal line at 79 mm intervals. Hang the control box onto the impact anchors using the dedicated holes 
at the rear of the box's body.

CAUTION! 

The control box shall be mounted within no more than 5 m from the switching unit. If the 

distance between the control box and the switching unit exceeds 5 m, avoid extending the standard 
cable; instead, use a 4x0.2 KSPVG cable (PE-insulated PVC-sheathed flexible communication cable) 
of appropriate length with TP 4p4c (RJ11) connectors, and follow the wiring sequence applicable to 
the standard cable. 
The switching unit shall be mounted outside of the steam room using two impact anchors with a di-
ameter of 6 mm. The switching unit can be installed inside a switchboard or covered with a panel 
cover.
The  temperature  sensor  shall  be  installed  inside  the  steam  room.  For  accurate  readings,  the  sensor 
should be placed directly above the electric heater 1.8 to 2.0 m above the floor and at least 1.2 to 1.5 
m above the sauna heater.
An installation contractor's representative putting the control unit into operation shall brief the user 
on safe operation and maintenance of the control unit, and specify which operations can be done by 
the user and which ones require a qualified serviceman.
The installation contractor's representative shall make a record and sign and stamp the warranty cer-
tificate. Without such records the warranty certificate shall be considered invalid and the manufacturer 

SAUNA HEATERS, GARDEN FIRE PITS, SOLID FUEL BOILERS

Summary of Contents for EOS-CONTROL 18

Page 1: ...PERATING MANUAL GEOS SAUNA HEATER CONTROL UNIT Please read this instruction manual carefully before installing and using the control unit Keep it at hand throughout the entire life of the control unit...

Page 2: ...C E I N F O R M E D C H O I C E O B V I O U S A D V A N O B V I O U S A D V A N T A G E S O B V I O U S A D V A N T A G E S I N F O R M E D C H O I C E I N F O R M E D C H O I C E O B V I O U S A D V...

Page 3: ...ty valid CAUTION See that the retailer and the installation and maintenance contractors have lled in respective sections of the OM Remember that if the retailer fails to execute the Certi cate of Sale...

Page 4: ...Electric heater operating parameters adjustment mode Operation mode In the operation mode the control unit ensures the following electric heater operating conditions Heating of the steam room In this...

Page 5: ...plate 12 Control board 13 Knob 14 End cover 15 3 Fig 1b Control box Fig 1a General view 10 11 13 14 15 12 1 5 6 7 380 1 2 3 4 7 5000max 5000max SAUNA HEATERS GARDEN FIRE PITS SOLID FUEL BOILERS The bo...

Page 6: ...ch on delayed start 10 5 Switching unit Fig 1d Body 20 Cover 21 Terminal block 22 Switching unit board 23 10 1 14 10 2 10 4 10 5 10 3 Fig 1d Switching unit The switching unit comprises a body 20 with...

Page 7: ...5 To 3 phase mains To the electric heater To single phase mains N To single phase mains L1 Using jumpers To single phase mains To the electric heater SAUNA HEATERS GARDEN FIRE PITS SOLID FUEL BOILERS...

Page 8: ...connected in accordance with PUE and GOST R IEC 60335 2 53 by certi ed electricians with an electrical safety access quali cation level III or higher CAUTION Before connecting and installing the cont...

Page 9: ...wall in one horizon tal line at 79 mm intervals Hang the control box onto the impact anchors using the dedicated holes at the rear of the box s body CAUTION The control box shall be mounted within no...

Page 10: ...play the parameters All adjustments are made by pressing and turning the encoder knob To switch the control unit on or off press and hold the knob for 2 s to switch from one adjustment mode to another...

Page 11: ...he default delayed start time is zero If you skip this setting press the encoder knob but do not set the delayed start time the control unit will switch to the ON mode Operating modes of the control u...

Page 12: ...nsor is connected Replace the temperature sensor Replace the temperature sensor Check the control cable Replace the temperature sensor Switching the control unit off To switch the control unit off pre...

Page 13: ...nance instructions The user or a third party stored or transported the item in an improper manner The item was not used for its intended purpose The item was repaired by the user or a third party with...

Page 14: ...manufacture Quality inspector Packer Stamp here Certi cate of Sale Name of retailer Date of sale ____ ___________ 20____ Stamp of retailer I have no claims to the quality of the product Buyer s signat...

Page 15: ...n Connection Disconnection Connection Disconnection Record of warranty repair Description of defect Cause of malfunction Description of repair Date of repair ____ __________ 20____ Name of service con...

Page 16: ...Manufacturer Teslatec LLC 12 Permskaya St Novosibirsk 7 383 304 94 30 www teslatec ru Manufacture for Koster LLC 60 9 Stantsionnaya St Novosibirsk tel 7 383 328 47 77 www koster pro...

Reviews: