Safety instructions

1.  Read and strictly follow this installation and operating instructions to ensure a 

long life and reliable cylinder operation.

2.  The manufacturer of this cylinder will not be liable for any damages due to the 

failure to follow the installation and operation instructions.

3.  The cylinder must not be installed in rooms where the temperature may drop 

below 0°C.

4.  The  cylinder  installation  and  the  initial  start-up,  as  well  as  all  electrical  and 

hydraulic work must be performed by a qualified professional installer- in strict 

accordance with assembly and operating instructions.

5.  The cylinder is designed for standing vertical installation- screw on three feet.

6.  The device  must be installed in such a place and in such a way in order not to 

flood the room in case of the emergency water leak.

7.  Connections to water supply system, central heating system, and solar collec-

tors must be made in accordance with the diagram in this installation instruction. 

Failure to follow the installation instruction invalidate the warranty and may cause 

cylinder’s damage.

8.  Connections to water supply system must be made in accordance with the legally 

binding standards.

9.  The cylinder is a pressure appliance designed for connection to the water supply 

system where the water pressure doesn’t exceed 0,6 MPa. If the water pressure 

exceeds 0,6 MPa, the pressure reducing valve before cylinder must be fitted.

10.  A small leak from the safety valve through the outlet pipe may occur, it is a normal 

operating state of the appliance. The outlet of the pipe has to remain open. Do 

not clog it, as a clogged outlet may cause cylinder’s breakdown.

11.  Do not use the cylinder if you suspect that the safety valve may be faulty.

12.  The tank is equipped with a magnesium anode - an additional protection against 

corrosion. The anode is an operating part, therefore, it is exposed to wear.

 

The  condition  of  the  magnesium  anode  should  be  controlled  every  12 

months. The anode must be replaced once every 18 months.

13.  Rated temperature of water in the cylinder should not exceed 80°C.