SERVICE PROCEDURE
MAINTENANCE
4-44
EVERY 250 HOURS SERVICE
4
Maintenance for every 50 hours service should be carried out at the same time.
LUBRICATING
4
1.
Lower the blade to the ground, then stop the engine.
2.
Using a grease pump, pump in grease through the grease fittings shown by arrows.
3.
After greasing, wipe off any old grease that was pushed out.
POWER TILTDOZER
(1) Lift cylinder support yoke (4 places)
(2) Lift cylinder support shaft (2 places)
(3) Lift cylinder ball joint (2 places)
(4) Tilt cylinder ball joint (1 place)
(5) Tilt brace ball joint (1 place)
(6) Brace ball joint (2 places)
(7) Tilt brace thread (1 place) (screw-adjustable)
POWER TILT-POWER PITCH DOZER
(1) Lift cylinder support yoke (4 places)
(2) Lift cylinder support shaft (2 places)
Summary of Contents for 69001
Page 2: ......
Page 3: ...FOREWORD 11 ...
Page 24: ...CONTENTS 1 22 ...
Page 54: ...PRECAUTIONS FOR MACHINE SAFETY 2 30 ...
Page 177: ...OPERATION TROUBLESHOOTING 3 123 ...
Page 178: ...TROUBLESHOOTING OPERATION 3 124 ...
Page 253: ...SPECIFICATIONS 15 ...
Page 270: ...EQUIPPING FIRE EXTINGUISHER AND FIRST AID KIT ATTACHMENTS OPTIONS 6 16 ...
Page 271: ...INDEX 17 ...
Page 272: ...INDEX 7 2 ...
Page 275: ...COLOPHON 18 ...