Illustration 7–1 BACnet MS/TP network wiring
MS/TP
+B
A
RS
OAT
GND
DAT
ECON
G
Y1
Y2
RC
W1
W2
RH
AO6
AO7
COM
24VAC
The controllers or devices on the physical ends of the MS/TP wiring segment
must have end-of-line (EOL) termination installed for proper network
operation. See
Location for end-of-line termination
. Set the
end-of-line termination to On using the EOL switches.
Illustration 7–2 Location for end-of-line termination
EOL On
EOL On
Off
Off
shows the position of the EOL switches in
the AppStat controller.
Section 7: System integration
KMC Controls, Inc.
122
Revision G
Summary of Contents for BAC-4000 series
Page 6: ...Contents KMC Controls Inc 6 Revision G ...
Page 30: ...Section 2 Installing the AppStat KMC Controls Inc 30 Revision G ...
Page 64: ...Section 4 Commissioning functions KMC Controls Inc 64 Revision G ...
Page 112: ...Section 6 Application drawings KMC Controls Inc 112 Revision G ...
Page 124: ...Section 7 System integration KMC Controls Inc 124 Revision G ...
Page 128: ...power 28 roof top unit 98 rough in 18 Index KMC Controls Inc 128 Revision G ...