8.9.6.
With Air Compressor in place, adjust Bracket side-to-side, as required to maintain at l
east 1/8” clearance
between Air Compressor Head and Rack, as shown below. Once position is obtained,
final torque Rear
Bolt of Rack to 49 lbf-in.
Figure 22
–
Air Compressor Clearance Adjustment (Shown installed on CARB Vehicle)
8.9.7.
Remove Air Compressor from Bracket and set aside. This is necessary to gain proper access to Hex
Coupling nut (i.e.,
) inserted inside Rack Support Tube.
8.9.8.
With Bracket properly positioned,
final torque Front Bolts of Rack to 72 lbf-in and 49 lbf-in
, as shown
above in
Figure 23
–
Air Compressor Bracket final installed (Shown installed on CARB Vehicle)
1/8” MIN. CLEARANCE
BETWEEN HEAD AND RACK
FRONT
Adjust Bracket Side-to-Side