28
End Truck
Bridge Beam
Brace
Brace
Figure 3-8
Another way is to install your crane system is to first assemble the crane on the floor
beneath the runway/rails. Then lift the crane into position as shown in Figure 3-9.
Travel Rail
Figure 3-9
When installing the hoist and trolley on the bridge beam, refer to the installation
instructions for your hoist and trolley.
3.3
Max-E-Lift End Trucks
(for Double Girder Crane Systems)
3.3.1
Assemble and install the Max E Lift cranes using the appropriate information in section 3.1 or 3.2
based on whether your Max E Lift system is underhung or top running.
3.3.2
Refer to Figure 3-10 and verify the following:
a) End Truck Alignment - verify A = B and X = Y.
b) Bridge Beams/Rails Alignment - Ensure that the bridge beams/rails conform to the
manufacturer's requirements for the trolley/hoist (e.g. Parallelism, squareness, rail size,
clearances, and gauge).