CED MANUAL
SECTION:
DM
PREPARED BY: BKC
DM0122
DATE: 4-7-20
A
COMPANY
BETTER SOLUTIONS. BETTER BUILDINGS.
DM0122
K
INSULATED TRANSLUCENT PANEL INSTALLATION INSTRUCTION FOR PURLINN SPACING OTHER THAN 5'-0"
ROOF PURLIN
UP
SLO
PE
OUTER TRANSLUCENT PANEL
'H9320'
PREVIOUS PANEL RUN
DOWN SLOPE
ROOF PANEL
UPSLOPE PANEL
INNER TRANSLUCENT PANEL MK.
'H9320'
UNDER DOWNSLOPE AND PREVIOUS
PANEL EDGES
ERECTOR NOTES
1. ERECT TRANSLUCENT PANEL IN THE SAME SEQUENCE AS A METAL
PANEL (U.N.O.).INNER TRANSLUCENT PANEL UNDERNEATH THE
PREVIOUS AND DOWN SLOPE PANELS.
2. BE SURE TRANSLUCENT PANEL & TAPE SEALANT ARE FREE OF DUST
& DEBRIS BEFORE INSTALLATION. ALL PANELS & MASTIC MUST BE
ASSEMBLED BEFORE FASTENERS ARE INSTALLED.
3. FASTENERS MUST PENETRATE THE TAPE SEALANT.
4. USE 3/16" x 7/8" TAPE SEALANT AT ALL LAPS AND PANEL STRAPS.
5. NEVER STEP, STAND OR APPLY WEIGHT TO TRANSLUCENT PANELS.
SEC
TIO
N B
SEC
TIO
N A
INSIDE CLOSURE
'H3440'
INSIDE CLOSURE
'H3440'
3/16" x 7/8" TAPE
SEALANT
'H3440'
INSIDE CLOSURE
INSIDE CLOSURE
'H3440'
SIDE STRAP
'TPK'
UNDER BOTH SIDELAPS AS SHOWN
IN SECTIONS "A" & "B"
(THE STRAP DOES NOT ATTACH
TO THE PURLINS)