SDA
Lüftungskomponenten
Assembly, installation and operating instructions
13
Fig. 4: Height adjustment
Use a screwdriver to screw in the adjusting screws.
Align the plenum box and use the adjusting screws to set the provisional
height of the raised floor height adjustment feet.
Using installation aids on site, fix the plenum box to the floor with
rawlplugs and screws.
Fig. 5: Delivery condition of the connecting
panels
With strip installations, the connecting panels are pre-installed as shown
when delivered.
Fig. 6: Loosening the screws of the connecting
panel
Loosen the screws of the connecting panels and move the connecting panel
so that 2 plenum boxes can be connected together (similarly to the left-
hand connecting panel in the figure).
Fig. 7: Screwing the plenum boxes together
Connect plenum boxes installed in series on site to the next box using the
connecting panels.