QFX5220 Clearance Requirements for Airflow and Hardware Maintenance
When planning the site for installing a QFX5220, you must allow sufficient clearance around the installed
chassis (see
and
Figure 29: Clearance Requirements for Airflow and Hardware Maintenance for a QFX5220-32CD
g051087
18.99 in.
(48.23 cm)
Clearance required
for maintenance
22.79 in. (57.88 cm)
FRUs
Ports
17.26 in.
(43.84 cm)
Clearance required
for maintenance
21.1 in. (53.59 cm)
30 in. (76.2 cm)
24 in. (61.0 cm)
Figure 30: Clearance Requirements for Airflow and Hardware Maintenance for a QFX5220-128C
g051193
FRUs
19.0 in.
(48.23 cm)
Ports
17.32 in.
(44.00 cm)
29.00 in. (73.66 cm)
Clearance required
for maintenance
29.25 in. (74.30 cm)
Clearance required
for maintenance
30 in. (76.2 cm)
24 in. (61.0 cm)
•
For the cooling system to function properly, the airflow around the chassis must be unrestricted. See
“QFX5220 Cooling System” on page 52
for more information about the airflow through the chassis.
86
Summary of Contents for QFX5220
Page 1: ...QFX5220 Switch Hardware Guide Published 2019 11 07 ...
Page 18: ......
Page 77: ......
Page 107: ......
Page 148: ......
Page 172: ...5 CHAPTER Troubleshooting Hardware Troubleshooting the QFX5220 179 ...
Page 173: ......
Page 182: ......
Page 206: ...Restricted Access Warning 213 ...
Page 221: ...Jewelry Removal Warning 228 ...
Page 224: ...Operating Temperature Warning 231 ...
Page 234: ...DC Power Disconnection Warning 241 ...
Page 238: ...DC Power Wiring Sequence Warning 245 ...