Johnson Controls Split Wall-Mounted Type Installation Manual Download Page 2

3. REFRIGERANT PIPING CONNECTION

Rough-mess

Burr

2. Tightening Connection

CAUTION

Align pipes to be connected.
Sufficiently tighten the flare nut with fingers,
and then tighten it with a spanner and torque
wrench as shown.

Excessive torque can break nut depending
on installation conditions.

2. Insert a flare nut into a pipe and flare the
    pipe.

 Min.

0.7

1.0

Outer
diam.

6.35mm

12.7mm

Tightening
torque (N.cm)

1570

(160kgf.cm)

4900

(500kgf.cm)

Additional tightening
torque (N.cm)

1950

(200kgf.cm)

5390

(550kgf.cm)

Install the outdoor unit on a rigid base to prevent increasing
noise level and vibration.
Determine the air outlet direction where the discharged or 
radiating  air is not blocked.
In the case that the installation place is exposed to strong wind
such as a  seaside  or  high  position,  secure  the  normal  fan  operation by putting the unit
lengthwise along the wall or using a dust shield plates.
Specially in windy area, install the unit to prevent the admission of wind.
If  need  suspending  installation,  the  installation  bracket   should   accord  with   technique
requirement in the installation bracket diagram. The  installation  wall  should  be  solid brick, 
concrete or  the same intensity construction, or actions to reinforce, damping, supporting 
should be taken.The connection between bracket  and  wall, bracket and the air conditioner
 should be firm, stable and reliable.

Seal

Seal

Drain elbow

Drain elbow

The base pan
hole of outdoor
unit

The base pan of
outdoor unit

Fit the seal into the drain elbow, then
insert the drain elbow  into  the base
pan hole of outdoor unit, rotate 90 to 
securely assemble them. Connecting
the  drain  elbow  with  an  extension
drain  hose  (Locally  purchased),  in
case  of  the  water  draining  off  the 
outdoor unit during the heating mode.

(L-5M)X30g

Additional amount of 
refrigerant to be charged

When relocate  the unit  to  another place,
perform evacuation using vacuum pump. 

Open  the  valve  stem  until it hits  against the
stopper.  Do not try to open  it further.
Securely  tighten  the  valve  stem  cap with  a
spanner  or  the like.
Valve stem cap tightening torque.
Gas pipe side (  12.7):4900N.cm (500kgf.cm)
Liquid pipe side (  6.35):1570N.cm (160kgf.cm)

AIR PURGE AND TEST OPERATION

3

Perform  test  operation  after completing gas
leak  check at  the  flare  nut connections and
electrical safety check.
1. Connect  the  power,   push  the  ON/OFF
    button  on  the  remote  controller  to begin
    testing.
2. Push mode button, select cooling, heating,
    fan mode to check if all the functions works
    well.
3. If you can't find the Remote controller or the
    battery of the Remote controller has given
    out, manually operation  can  be  taken for
    the moment. 
    1) Open the front panel of the indoor unit;
        push the "COOL" button on the electrical
        control box. 
    2) Connect the power,  the air conditioner

        begin to operate,  check  if  there is any

        A  protection  feature  prevents   the  air

from   being   activated  for

  restarted

        immediately after operation or when the

 switch is turned on.

4. Press "AUTO" button again after finishing

operation. Then installer should

manipulate, fix and maintain

 tell  them  that

    regular check  of  the installation bracket 

    and  maintenance are necessary. Clients 

  for  inspecting to relevant

 the  air

    conditioner  can  operate  normally,  safely

reliably.

3. TEST OPERATION

Make sure no gas from connections with leak
detector or soap water.

2. GAS LEAK CHECK

Using the Vacuum Pump

Flare nut

Stopper

Manifold valve

Compound meter

-76cmHg

Handle Lo

Handle Hi

Charge hose

Charge hose

Vacuum pump

Low pressure valve at the gas pipe side

Pressure gauge

Cap

(For method  of  using a manifold valve, refer  to
its operation manual.)
1. Completely tighten the flare nuts  A, B, C, D,
    connect the manifold valve charge hose to a
    charge port of the packed valve  on  the gas
    pipe side.
2. Connect the charge hose connection  to  the
    vacuum pump.
3. Fully open the handle Lo of the manifold valve.
4. Operate the vacuum pump to evacuate. After
    starting evacuation, slightly loose the flare nut
    of  the packed valve on the gas pipe side and
    check that the air is entering.(Operation noise
    of  the  vacuum  pump  changes  and  a  com-
    pound meter indicates 0 instead of minus)
5. After the evacuation  is  complete, fully close
    the handle Lo of the manifold valve and stop
    the operation of the vacuum pump.
    Make evacuation for 15 minutes and more
    and check that the compound meter indicates
    -76cmHg.
6. Turn the stem of the packed valve B about 45
    counterclockwise,  securely  tighten  the  flare
    nut after 6-7 seconds. Make sure the pressure
    display in the pressure gauge is a little higher 
    than atmosphere pressure.
7. Fully open the packed valves B and A.
8. Securely tighten the cap of the packed valve.

CAUTION

A: Lo packed valve B: Hi packed valve
C and D are ends of indoor unit connection.

Indoor unit
check point

D

B

C

A

Outdoor unit
check point

Electrical box

1. Remove the electric parts cover from the  outdoor
    unit.
2. Connect the connective cables to the terminals as
    identified  with their respective  matched numbers
    on the terminal block of indoor and outdoor units.
    Connect the ground wire to the ground screw,
    the washer under the screw must touch the electr-
    ical installation plate.
3. To prevent  the ingress of water, from a loop of the
    connective cable  as  illustrated  in  the installation
    diagram of indoor and outdoor units.
4. Insulate unused cords (conductors) with PVC-tape.
    Process  them  so  they do not touch any electrical
    or metal parts.

4. WIRING CONNECTION

Electric parts cover

CAUTION

Wrong wiring connections may cause some electrical
parts to malfunction.

Terminal block of outdoor unit

1

1

3

4

2(N)

2(N)

Wire-holding

board

Oblique

1. Flaring

OUTDOOR UNIT INSTALLATION

2

1. Cut a pipe with a pipe cutter.

Outer diam.

(mm)

A(mm)

 Max.

1.3

1.8

C

90

A

1. OUTDOOR INSTALLATION PRECAUTION

Strong
wind

2. DRAIN ELBOW INSTALLATION

Air purging
method

Use vacuum
pump 

Use vacuum
pump 

        abnormal.

        about  3  minutes when  it  is

    explain how to 

    their air conditioner.  Also

    should   apply 

    department  so  as  to  ensure 

Choose purge method from the table:

Outdoor unit Refrigerant      Indoor unit

Valve stem

Valve body

Half union

1. AIR PURGE

CAUTION IN HANDING THE PACKED VALVE

AUTO
COOL

Tickle-type switch

12.7mm

C

D

6.35mm

  2200019361     CS0163

 

6.35

12.7

Connective

pipe Length(L)

Less than 5m

5   10m

        conditioner  

        power

    the test 

    and 

Packed valve

A

B

~

INDOOR UNIT INSTALLATION

1

5. PIPING AND BANDAGING

Right-hand piping

Left-hand piping

Rear-right piping

Rear-left piping

Connective piping

Connective cable

Drain hose

Tape

CAUTION

1. For  the  left-hand and right-hand piping,  remove
    the pipe cover from the side panel.
    Explain to clients that the pipe cover must be  kept
    as it may be used when relocate the air conditioner
    to any other place.
2. Wind the connective cable, drain hose and wiring
    with tape securely, evenly.

Install the drain hose at the bottom of the connective cable.
Reasonably and carefully arrange and bandage the piping in case
to damage the drain hose and connective piping.

Make sure to run the drain hose sloped downward to drain out the
condensation smoothly.
Never intercross or intertwist power line with any other wiring.

. .

..

.

. .

. . . .

.

. .

.

. .

..

.

..

.

.

.

.

.

.

.

.

.

.

CAUTION: