About this guide
This quick start guide provides the basic information you
need to configure and install the Verasys
®
Equipment
Controller (VEC), LC-VEC100-0, using the Verasys generic
rooftop unit (RTU) staged heating and staged cooling
controller application. The application controls a third-
party changeover bypass (COBP) system or a third-party
variable air volume (VAV) unit.
For further information, refer to the
Verasys Equipment
Controller (VEC) Installation Guide (24-10143-1272)
and the
VEC100 Generic RTU Controller, Staged Heating and Staged
Cooling Application Note (12013443)
.
Table 1: Application features
Options available Possible values
Number of Heating
Stages Installed
0 to 2
Number of Cooling
Stages Installed
0 to 4
Economizer
Installed
•
State 0: the economizer is not
available.
•
State 1: the economizer is available.
Air Proving Switch
Setup
•
State 0: fan status device
•
State 1: duct static pressure sensor
•
State 2: none
Rooftop Controller
Type
•
State 0: changeover bypass
•
State 1: VAV
Cancel ASCD Timers •
State 0: false
•
State 1: true
Demand Ventilation
Feature
•
State 0: demand ventilation is off.
•
State 1: demand ventilation is on.
Mounting the controller
To mount the controller, complete the following steps:
1. Mount a 20 cm (8 in.) section of 35 mm (1.3 in.) DIN
rail horizontally.
Note:
Mount the controller in the horizontal
position.
2. On the back of the controller, extend the two
mounting clips.
Figure 1: Pull down lower mounting clips
3. Place the controller on the DIN rail.
4. Push the bottom mounting clips inward (up) to
secure the controller on the DIN rail.
Figure 2: Push up lower mounting clips
Wiring the controller
Zone bus terminal block
The zone bus terminal block is a grey, removable, 4-
terminal plug that fits into a board-mounted jack. Wire the
removable zone bus terminal block plugs on the controller
on the top row of the stacked connector, and other field
controllers in a daisy-chain configuration using 3-wire
twisted, shielded cable as shown in the following figure.