background image

FD-1600 1-1/2 Hour Dynamic Rated Multi-Blade Fire Dampers Installation Instructions 

3

Flange breakaway connection for fire damper or 
combination fire smoke damper. These instructions 
apply to a connection between a manufactured 
flange system by a specific manufacturer 
(Ductmate® Industries, Inc.) or connection styles 
produced by several manufacturers (Nexus, TDC 
and TDF). These connections allow the use of 
combining mixed flange types or like for like. The 
following instruction depicts the use of metal or 
plastic cleats, a butyl or neoprene gasket, and 
bolted or non-bolted corners. Also the flanges may 
be connected with the use of #10 screws without 
the cleats.

a.

Install the manufactured flange system onto 
the damper sleeve or duct per the 
manufacturers instructions.

b.

Seal the two flange systems together. 
Neoprene or Butyl gasket may be applied to 
the mating surfaces.

c.

Align the two flange systems together. A 3/8 in. 
(9 mm) bolt may be used in the corners to help 
with the alignment.The bolt does not have to 
be removed. Bolted corners are permitted.

d.

Install the cleat or # 10 tek screw, 
approximately equally spaced, per the 
schedule described:

e.

Install the cleat or # 10 tek screw, 
approximately equally spaced, as indicated in 
Table 2.

  

Table 2:  Cleat or Screw Spacing

Width or Height

Screws or Cleats 
per side

Less than 24 in. (610 mm)

1

24 in. (610 mm) to less than 
36 in. (914 mm)

2

36 in. (914 mm) to less than 
54 in. (1,372 mm)

3

54 in. (1,372 mm) to less than 
72 in. (1,829 mm)

4

72 in. (1,829 mm) or greater

5

Figure 1: Flanged System Breakaway Connections

Reviews: