Johnson Controls E-Link Installation Instructions Manual Download Page 1

E-Link Gateway Installation Instructions

1

Applications

The E-Link Gateway provides Johnson Controls® and 
YORK® mechanical equipment, such as chillers and 
rooftop units, with Building Automation System (BAS) 
networking connectivity. It is designed with three active 
serial ports: Port 1 and Port 4 are used for BAS 
networking, Port 2 is reserved for connecting to the 
equipment, and Port 3 provides access for auxiliary 
monitoring and control.

To simplify the installation and setup, the E-Link 
Gateway comes pre-configured with a series of chiller 
and rooftop equipment profiles that you can choose by 
selecting the correct DIP switch settings.

Several E-Link Gateway models are available for 
connection to various types of input voltage and 
equipment. For chillers using the OptiView™ or 
Latitude Micro Panel, the E-Link Gateway consists of a 
single circuit board attached to four studs inside the 
Micro Panel, using the accessory mounting kit. The 
panel supplies 12 VDC input power, eliminating the 
need for an external power supply.

For chillers using the IPU-II based Micro Panel, the 
E-Link Gateway is installed inside the Micro Panel and 
requires an additional transformer to supply power to 
the E-Link Gateway. The transformer is included in the 
E-Link IPU-II Installation Kit. (This kit is not available in 
Europe. Use E-Link Gateway YK-ELNKE00-0.)

For other types of chillers, the E-Link Gateway is 
packaged in its own enclosure. In addition to the E-Link 
Gateway circuit board, a transformer is included inside 
the enclosure that converts a 120- or 240-volt input to 
24 VAC power.

North American Emissions Compliance

United States

Canada

Installation

The E-Link Gateway is supplied as a circuit board that 
can be installed directly into the equipment’s enclosure, 
or can be supplied pre-mounted in an enclosure ready 
for line voltage. Accessory mounting kits are used to 
mount the E-link Gateway directly into OptiView 
Latitude, and IPU-II based Micro Panels.       

This equipment has been tested and found to 
comply with the limits for a Class A digital device 
pursuant to Part 15 of the FCC Rules. These limits 
are designed to provide reasonable protection 
against harmful interference when this equipment is 
operated in a commercial environment. This 
equipment generates, uses, and can radiate radio 
frequency energy and, if not installed and used in 
accordance with the instruction manual, may cause 
harmful interference to radio communications. 
Operation of this equipment in a residential area is 
likely to cause harmful interference, in which case 
the user will be required to correct the interference 
at his/her own expense.

This Class (A) digital apparatus meets all the 
requirements of the Canadian Interference-Causing 
Equipment Regulations.

Cet appareil numérique de la Classe (A) respecte 
toutes les exigences du Règlement sur le matériel 
brouilleur du Canada.

IMPORTANT:

Do not install the E-Link Gateway 

directly into an equipment’s enclosure without the 
use of an approved installation kit.

E-Link Gateway

Installation Instructions

Part No. 24-10404-9, Rev. D

Issued November 2, 2011

Supersedes April 29, 2011

Summary of Contents for E-Link

Page 1: ...Gateway circuit board a transformer is included inside the enclosure that converts a 120 or 240 volt input to 24 VAC power North American Emissions Compliance United States Canada Installation The E...

Page 2: ...YLPA 031 01095 YORK Talk 2 4 800 bps YCAS YCWS YCRS 031 02478 YORK Talk 2 4 800 bps YCAV YCIV YVAA 031 01065 YORK Talk 2 1 200 bps YIA YPC YG YB 031 01730 YORK Talk 3 YN OM RETROFITS CR 031 02430 YORK...

Page 3: ...re jumper JP27 is set for RS 232 see Figure 20 6 Connect the power harness included with the kit from J2 on the E Link Gateway to J21 on the Optiview Micro Panel see Figure 20 The E Link Gateway is no...

Page 4: ...ground screw The E Link Gateway is now ready to be configured using Quick Start see the Commissioning a Standard Application section in this document Micro Board 24 VAC Transformer Expansion Nut Expa...

Page 5: ...ateway enclosure to the Micro Panel 6 Complete wiring as described in the Applying Power section in this document Note Use of bulkhead pipe couplers provides sufficient clearance to allow removal of t...

Page 6: ...e metal of both enclosures Scraping the paint around the knockouts usually helps provide a better electrical connection between the joining parts 1 Connect a 1 29 1 02 mm 16 18 AWG wire from a reliabl...

Page 7: ...to the Johnson Controls Portal Products and Services Delivery Products Service Field Support Equipment Integration YORK Equipment Data Maps 3 Press hold a few seconds then release the push button show...

Page 8: ...1 through 16 all use the J version point lists whereas Quick Starts 17 through 33 use the K version The primary difference between the two categories is that Quick Starts 1 through 16 have limited net...

Page 9: ...IPU I 17 0 1 0 0 0 1 YK with SSS Imperial YORK Talk III K version points 18 0 1 0 0 1 0 YK with VSD Imperial YORK Talk III K version points 19 0 1 0 0 1 1 YT with SSS Imperial YORK Talk III K version...

Page 10: ...600 N 8 1 Terminal 4 2 5 0 1 0 0 N2 9 600 N 8 1 MS TP 38 400 N 8 1 Terminal 5 2 5 0 1 0 1 Modbus 19 200 N 8 1 MS TP 38 400 N 8 1 Terminal 6 2 5 0 1 1 0 Modbus 19 200 N 8 2 MS TP 38 400 N 8 1 Terminal...

Page 11: ...nzorbs on each RS 485 port to protect against damaging electrical spikes and stray voltage The equipment panel should also be equipped with protection against electrical disturbances Whereas OptiView...

Page 12: ...ctivity RS 485 The RS 485 standard uses three conductors to connect network nodes two signal wires and a reference The E Link Gateway uses either a third wire for the reference or the building s infra...

Page 13: ...ch setting 1 Since the E Link Gateway uses a one to one relationship with the chiller panel this switch is normally set to 0 YORK Talk address 1 However in a master slave configuration set the master...

Page 14: ...itude POWER HARNESS Latitude 3 8 in Screw 8 x 32 OptiView 2 Position Connector 4 Position Connector 4 Position Connector 4 Position Connector Screw Tap Thread M4 x 32 mm Latitude FIG OptiVwKt YMC2 COM...

Page 15: ...Transformer Primary Power Wiring Harness Communication Wiring Harness Resistor Secondary Power Wiring Harness Tie Wrap FIG IPUII Kt Figure 15 E Link IPU II Panel Installation Kit YK ELNKSTK 0 Contents...

Page 16: ...is dated after 11 2000 the chiller ID is software selectable through the micro panel SHIELD BLUE WHITE Open 031 02050 000 TB1 TB6 NOTE The chiller ID is software selectable through the micro panel ke...

Page 17: ...E Link Gateway Installation Instructions 17 Figure 18 E Link Gateway to YORK Talk II Equipment Connections Continued See Table 1 for board cross reference...

Page 18: ...s in locations U4 and U5 The transfer rate on the chiller must be set to 4800 baud Frick RWBII Plus Jumpers Jumpers RWBII Rev B and Lower RX Jumpers RWBII Rev C and Higher U5 U4 Port 2 Port 1 SHIELD P...

Page 19: ...lk 3 Rs232 Optiview Microboard 031 01730 XXX SHIELD PORT 2B RS232 TX RX COMSHLD Open E Link E Link 12 VDC SHIELD Open Equipment Cable York Talk 2 RS485 4800 baud SHIELD COM SHLD PORT 2A RS485 Open E L...

Page 20: ...xxx I O Board 331 02496 101 IPU I Board YPAL ECO2 1 J4 2 3 4 5 P3 P3 GND 5V Equipment Cable BACnet MS TP 38400 baud FIG YPAL YPAL ECO2 Setup for MS TP Bus BLUE WHITE SHIELD GRD COM SHLD PORT 2A RS485...

Page 21: ...s a pre wired E Link Port 2 Terminal Block RS485 4800 baud SHIELD PORT 2A RS485 Open E Link 031 02550 xxx I O Board 031 02630 xxx IPU II Board T 1 RS485 REF SHLD IPU II P1 Setup for York Talk 2 FIG ST...

Page 22: ...E Link Gateway Installation Instructions 22 Figure 23 E Link Gateway to Wuxi STC YEWS D1 YEAS YGAS Equipment Connection Fig wuxi_stc...

Page 23: ...E Link Gateway Installation Instructions 23 Figure 24 E Link Gateway Communication Port Connections to a BAS System...

Page 24: ...if this connection has not been made elsewhere in the configuration Repair Information If the E Link Gateway fails to operate within its specifications replace the unit For a replacement E Link Gatew...

Page 25: ...PP Switch Group A 6 Position Dip Switch Port 2A RS485 Equipment Port Supporting BACnet MS TP and YORK Talk II Protocols with Available EOL Termination Switch Port 2B RS232 Equipment Port Supporting YO...

Page 26: ...Installation Instructions 26 Metasys and Johnson Controls are registered trademarks of Johnson Controls Inc All other marks herein are the marks of their respective owners 2011 Johnson Controls Inc Bu...

Reviews: