Installation, Operation, & Maintenance Instructions

 

IOM M500.01  March 2017 

MAGNICATOR

®

  

PRECAUTIONS: 

 

To obtain performance from your Magnetic Level Indicator (MLI), the following precautions should be observed. 

 

1. For Mini-Magnicator, refer to specific float instructions on page 3. 

 

2. The float chamber and float contained in your Magnicator are designed and manufactured to meet the exact 

specifications for your particular process conditions.  Do not use this indicator with liquids of different 

densities or under different operating process conditions for which it is rated without careful review of the 

new application. 

 

3. The Magnicator must be operated in an area free of magnetic forces or matter which will influence the 

magnetic circuit.  This includes items such as steel support straps, heater wires, and steel steam trace 

tubing.  Generally speaking, all carbon steel material should be kept at least 12 inches (305mm) away from 

the MLG column.  Contact the factory if this clearance cannot be obtained. 

 

4. Do not hydrostatic test the magnetic level indicator with the float inside the chamber.  The float is designed 

for maximum operating pressure only.  Exceeding of this pressure may affect the performance of the float. 

 

5. On models BEF, care must be taken not to bend or deform extension rod, as this may hinder the float 

movement. 

 

6. Check tag number and serial number engraved on float, and confirm they match the information located on 

the nameplate of the MLI chamber. 

 

INSTALLATION: 

 

To install your Magnicator, perform the steps described below. 

 

1. Unpack and inspect each unit upon receipt.  The float is removed from the Magnicator and packed in a 

protective tube that is temporarily attached behind the indicator scale for shipment.  The float should remain 

in this protective tube until it will be installed inside the MLI chamber. 

 

2. The MLI must be installed vertically and level. 

 

3. Block valves should be installed between the process vessel and the MLI.  

 

4. Composition gaskets are supplied for the access flanges.  If composition gaskets are not suitable for your 

process, appropriate gaskets should be used.  Check tag and serial number of float to assure correct match.  

Remove tag prior to operation. 

 

5. Install float, be sure to remove the instruction tag and to clean off any foreign matter, especially metal 

particles which may have become attracted to the magnet assembly inside the float.  The top of the float is 

marked and must be installed toward the top of the MLI. 

 

 

For Model EF (End Flanged)  

Float stop plates with springs are supplied and should be installed between the Magnicator and mating 

flange/block valves 

 

For Model BEF (Bottom End Flanged) 

Floats are factory installed on top mount level indicators and packed to protect it from damage.  Remove all the 

packing material before installation. 