Read instructions before starting installation*
For purposes other than water, contact JCM Industries for application and product assistance.

1.

Clean and scrape pipe. Remove any scale, pipe wrap, debris or dirt that may interfere
with the complete sealing of the gasket. Inspect pipe for integrity, size, outside
diameter and surface irregularities. Confirm the proper size and range of repair clamp.
Inspect fitting to ensure all parts are included.

For fittings furnished with stainless steel hardware, see reverse for fastener
management.

2.

Lubricate the pipe and the fitting gasket with soapy water. 

Do not use oil base pipe

lubricant.

3

.

Install the gasket (key locked cut for installation) on the spigot side of the joint with the
flat side facing toward the pipe bell. For large or oversized cast iron pipe an additional
“key cut” gasket extender has been included to lengthen the gasket if needed. Slide
the gasket toward the joint so that flat side of the gasket meets up with the face of the
bell (the tapered side will fit into the ductile iron pusher ring). Interlock the key locked
cut.

4.

Interlock the ductile iron clamp ring segments on the spigot side of the joint.

 Ensure

that the ductile iron clamp ring joint is rotated 90

o

 (1/4 turn) from the gasket joint.

On the bell side of the joint install the second set of clamp ring segments in the same
manner. Interlock the segments. To ensure proper gasket compression, rotate the
ductile iron clamp ring one bolt hole turn from the spigot ductile iron ring (

i.e. do not

align clamp ring joints or gasket joints

). Starting from the bell side to the spigot side,

install a track head bolt through the bolts holes to hold the segments together.
Complete installation by inserting the track head bolts through the segments and over
the joint into the corresponding bolt holes of the opposite clamp rings. Loosely
assemble nuts on the ends of the bolts. (Note: 8”, 10” and 12” fittings have an
additional set of long bolts to accommodate extended bells.)

5.

Hand tighten the nuts and ensure the ductile iron spigot ring is centered on the pipe
and is making full contact with the face of the gasket. Tighten the nuts evenly until the
spigot gasket compresses against the joint and the leak stops. Tighten nuts to
approximately 60 - 70 ft. lbs. of torque.

To ensure integrity of installation, wait 15 minutes, inspect for leaking, and confirm bolt
torque. If necessary, re-tighten bolts evenly as required to stop the leak.

*Ensure fitting is suitable for application (confirm size, materials, pressure ratings, line content, meets local governing & association standards, etc.).
Pipeline operation forces, including pressure fluctuations, thermal expansion/contraction, movement/shifting, etc. will influence the success of the
application. Proper anchorage, restraint, harnessing, thrust blocks or other devices must be provided to prevent pipe movement (lateral, angular, axial) or
pipe pullout from the bolt-on fitting. Inspection of the pipe integrity is the responsibility of the end user. JCM recommends the use of calibrated torque
wrench. Failure to follow installation instructions will result in voided product warranty.

For application review or questions contact JCM Industries at 1-800-527-8482, 903-832-2581

Installation Instructions

Model 

143 Bell Joint Leak Clamp

4” - 12” Ductile Iron, Cast Iron, C-900 PVC

INT143 4-12-0115

Reviews: