© 2020, JAPAN CASH MACHINE CO., LTD.
6 - 2 9
Calibration and Testing
UBA Pro RT/RQ™ Series Banknote Recycler
Section 6
7. Remove the Recycler from the RQ Transport to
block the Note Position Sensor D through F.
8. The RQ Unit’s Status LED will be lit at Magenta
when the Sensors function properly.
9. Set the UBA Pro DIP Switch #8 to
ON
to end the
test.
Recycler Solenoid Test (RQ Transport)
To run the Recycler Solenoid on the RQ Transport
side, proceed as follows:
1. Remove electrical power.
2. Set the DIP Switches of the UBA Pro Unit as
below (Figure 6-157).
3. Set the DIP Switches of the RQ Unit as below
4. Apply electrical power.
5. Confirm that the Status LED/Collect Button is lit
at
Green
Color and then turns off.
6. To start the Test, set the UBA Pro DIP Switch #8
to
OFF
7. The Solenoid will start operating when it func-
tions properly.
8. Set the UBA Pro DIP Switch #8 to
ON
to end the
test.
Drum 1 Motor Test (RQ Transport)
To run the Recycler Solenoid on the RQ Transport
side, proceed as follows:
1. Remove electrical power.
2. Set the DIP Switches of the UBA Pro Unit as
3. Set the DIP Switches of the RQ Unit as below
Figure 6-156
Figure 6-156
Note Position Sensor D - F Test
(RQ Transport) 5
Figure 6-157
Figure 6-157
Recycle Solenoid Test
(RQ Transport) 1
DIP Switches #1, #2, #6, #8 ON
ON
1
2
3
4
5
6
7
8
Figure 6-158
Figure 6-158
Recycle Solenoid Test
(RQ Transport) 2
DIP Switches #5, #8 ON
ON
1
2
3
4
5
6
7
8
NOTE: Wait for the Status LED to turn off
in order to run the test properly.
Figure 6-159
Figure 6-159
Recycle Solenoid Test
(RQ Transport) 3
Green
ON
OFF
Figure 6-160
Recycle Solenoid Test
(RQ Transport) 4
DIP Switch #8 OFF
ON
1
2
3
4
5
6
7
8
NOTE: Confirm the functionality aurally by
the sound that the Solenoid is making
while in the operation.
Figure 6-161
Drum 1 Motor Test (RQ Transport) 1
DIP Switches #1, #2, #6, #8 ON
ON
1
2
3
4
5
6
7
8
Figure 6-162
Drum 1 Motor Test (RQ Transport) 2
DIP Switches #6, #8 ON
ON
1
2
3
4
5
6
7
8