8
Please see operator manual for full details.
Lifting Points
Fig 4
Operation
Lifting the Machine
99
9831/2900-1
99
7. Check that the lifting eye is positioned directly above the machine centre of gravity.
Figure 84.
D
A
B
B
C
F
E
G
A
Boom lift point
B
Dozer blade lift point
C
Spreader bar
D
Centre of gravity
E
Dimension= 792mm (16C-1/19C-1), 632mm
(18Z-1)
F
Dimension= 639mm (16C-1/19C-1), 659mm
(18Z-1)
G
Dimension= 533mm (16C-1/19C-1), 525mm
(18Z-1)
Description
18z-1
19c-1
19c-1 PC
A
Boom Lift Point
B
Dozer Blade Lift Point
C
Spreader Bar
D
Centre of Gravity
E
mm
632
792
792
F
mm
659
639
639
G
mm
525
533
533
*COG = Centre of Gravity
The correct lifting positions are identified on the machine by their labels:
Lifting point
Position label.
Fig 5
REFER TO OPERATORS MANUAL TRANSPORTING MACHINE